At last night's council meeting: Ville de Montréal Auditor General tables his
report on the process for acquiring and installing water meters
This report follows City Council's
Assessing the price of the ICI contract as too high, the Auditor General said his review of documents and the interviews he conducted led him to conclude that "it is appropriate to examine all possibilities regarding continuation of the ICI and Network Optimization project in its present form, including cancelling the contract awarded to GÉNleau... ".
In his 176-page document containing 58 findings and 26 recommendations, the Auditor General looks at the unexpected addition of a second element to the water meters project: network optimization (real-time management of the network). He expresses "serious reservations about the way the initial project was modified and the speed with which the new network optimization element - which is very substantial from both the monetary and technology perspectives - was introduced and approved by the individuals responsible for the file." In other words, the initial mandate to install water meters in ICI locations was altered along the way.
The Auditor General believes that the ICI and Network Optimization project "does not meet current needs and does not optimize the cost-benefit ratio for the City."
As for ethnics and governance, the audit revealed that some meetings between representatives of the City and certain external partners involved in the ICI and Network Optimization project were scheduled during the call for qualifications in 2006 and between the call for qualifications and the call for proposals won by GÉNIeau. "We cannot confirm if these meetings took place or the subject of these meetings," the Auditor General writes in his report. "However, this information appears to raise doubts about the close ties between these individuals and about the influence that these meetings could have had on the development of the project."
Noting that he cannot comment further on this situation, since the file has been handed over to the Sûreté du Québec, the Auditor General does, however, add that calls for qualifications and calls for tenders should be much clearer as regards their instructions about complete independence between the City and its external partners, and between the external partners themselves.
Main findings
The main findings of the Auditor General's report are:
- The calls for qualifications and call for tenders or proposals that led to contracts with BPR (February 2005) and GÉNleau (November 2007) were not approved beforehand by the City's Executive Committee; - Decision summaries submitted to the Executive Committee said nothing about the state of progress of the ICI project between May 2004 and November 2007; - The network optimization element was not part of the first BRP mandate (installation of water meters in ICI locations). This aspect became an integral part of their mandate, with the decision being taken in an improvised fashion. The changes made to the call for proposals process raise questions about the thoroughness of the analysis done of the specifications mentioned in the initial call for proposals; - These changes would have required a new call-for-qualifications process and, as a result, a new call for tenders to allow businesses that had or would have had an interest in bidding to compete on equal footing; - Apparently, neither BPR, nor the City's project management office, nor its finance department, conducted an economic study of the expected benefits of the project, particularly the network optimization element; - The mandate given to BPR included several deliverables, some of which were not provided to the City; - Splitting the contract into several contracts of smaller scope would have provided certain economic benefits for the City; - Removing the project financing requirement at the call for proposals phase significantly undermines the very legitimacy of the process; - The contract awarded to GÉNleau totals $618 million, not $356 million, taking into account various additional fees; - The contract was awarded to GÉNleau in a way that did not encourage obtaining the best price; - The network optimization element of the water meters project does not meet the priority needs of the City at the current stage in the waterworks plan; - Based on the needs identified by the City, the ICI element appears to warrant the installation of water meters in ICI locations and a rate-setting process, as planned; - The City's legal department was not actively involved in the file from the outset, despite the scope of the project.
Recommendations
The Auditor General therefore recommends that the network optimization concept be revisited and its implementation envisaged at a later phase. In addition, before proceeding with work on this element, it would be necessary to locate major leaks and restore these pipes.
Regarding ethics and governance, he recommends the organization of ethics training for the elected officials, senior managers, supervisors and personnel involved in the contract procurement, acquisitions and implementation process. Governance practices for the management process should be reviewed. The City should create a study committee to review control mechanisms as well as the governance of the City of
For its part, City Council should appoint a committee made up of independent experts to examine the overall management process for the two other waterworks projects, including the action plan for the water mains and sewers networks, and the inspection and application of standards for water plants.
The Ville de
The other recommendations of the Auditor General are:
- The City's legal department should report directly to the General Manager so as to ensure the separation of functions from other City departments; - Calls for tenders for some large contracts should be accessible to firms outside Québec, without penalizing companies that have never dealt with the City; - The City should conduct a systematic and thorough evaluation of expected benefits before starting a project.
The mandate of the Auditor General of the Ville de
For further information: Patricia Lowe, Media Relations, Ville de Montreal, (514) 872-5467; Source: Office of the Auditor General
Share this article