221 new projects approved in 86 communities
THUNDER BAY, ON, May 24, 2017 /CNW/ - The governments of Canada and Ontario are committed to investing in local infrastructure that ensures Canadians and their families have access to modern, reliable water and wastewater services that meet their needs. These investments safeguard the health and well-being of residents, protect waterways and preserve local ecosystems, while also laying the foundation for new economic opportunities to strengthen the middle class across the province.
The Honourable Patty Hadju, Minister of Employment, Workforce Development and Labour, and Member of Parliament for Thunder Bay-Superior North, on behalf of the Honourable Amarjeet Sohi, Minister of Infrastructure and Communities, Bill Mauro, Member of Provincial Parliament for Thunder Bay-Atikokan, on behalf of the Honourable Bob Chiarelli, Ontario Minister of Infrastructure, and His Worship Keith Hobbs, Mayor of Thunder Bay, today announced that 34 new projects in Thunder Bay have been approved under the Government of Canada's Clean Water and Wastewater Fund. The federal government is providing up to 50 per cent of funding for these projects—over $5.5 million. The provincial government is providing up to 25 per cent of funding for these projects—just over $2.7 million of total eligible costs, and the City of Thunder Bay will provide the balance of funding.
Thanks to this investment, residents of Thunder Bay will benefit from city-wide stormwater infrastructure inventory assessment, as well as design and construction of 16 storm water management facilities. The region will also benefit from the construction of new stormsewers and outfalls to improve stormwater passage and capacity. These projects are essential to keeping our waterways clean and our communities healthy and livable.
In addition to these projects, over $13.6 million in federal funding for 187 water and wastewater projects will benefit 85 other communities across Ontario.
This investment is part of an agreement between Canada and Ontario for the Clean Water and Wastewater Fund.
Quotes
"Investing in water and wastewater treatment infrastructure is essential to maintaining a healthy environment and providing access to clean, reliable drinking water. The Government of Canada is working with provinces, territories and municipalities across the country to support important projects like those in Thunder Bay, which ensure that Canadian communities are healthy and sustainable now and for years to come."
The Honourable Patty Hadju, Minister of Employment, Workforce Development and Labour, and Member of Parliament for Thunder Bay-Superior North,
On behalf of the Honourable Amarjeet Sohi, Minister of Infrastructure and Communities
"These investments will mean real change for community members living in Thunder Bay and the region. Water and wastewater infrastructure are essential to the health and well-being of families across Northwestern Ontario and I am proud that our government recognizes the importance of reliable access to clean drinking water."
Don Rusnak, Member of Parliament for Thunder Bay-Rainy River
"The government of Ontario is proud to be investing almost $270 million in water and wastewater infrastructure for municipalities, First Nations and Local Services Boards across the province. We continue to invest in the kinds of infrastructure projects that keep our communities safe, provide reliable access to clean water, and protect our waterways."
Bill Mauro,
Member of Provincial Parliament for Thunder Bay-Atikokan
"The City of Thunder Bay is pleased to receive the $8.3 million in funding from the Federal and Provincial Governments. Thanks to this investment, our residents will benefit from infrastructure improvements that are essential to keeping our waterways clean and our community healthy. We appreciate the commitment to enhance local infrastructure that citizens rely and depend upon every day."
Keith Hobbs, Mayor of Thunder Bay
Quick facts
Related product
Backgrounder
Canada and Ontario announce funding for clean water and wastewater infrastructure projects across Ontario
221 new projects approved in 86 communities
A new list of water and wastewater projects has been approved under the Canada-Ontario Clean Water and Wastewater Fund (CWWF) agreement, which is designed to improve the safety and quality of water for Canadian families, while supporting a clean economy.
The Government of Canada is providing Ontario with over $569 million under CWWF (up to 50 percent of the eligible project costs). The provincial government is providing up to $270 million (up to 25 percent of total eligible project costs). The recipients will provide the balance of funding.
As part of the bilateral agreement with Ontario, the following 221 projects across Ontario have been approved for federal funding amounting to $19,219,318.
Location |
Project Name |
Federal |
Provincial Funding |
Anticipated Start Date |
Armstrong, Township of |
Upgrading of perimeter Safety and Security Fencing to Wastewater Lagoon |
$47,500 |
$23,750 |
June 1, 2017 |
Armstrong, Township of |
Rehabilitation of Well # 3 located on 6th Street including New Casing and pump |
$10,000 |
$5,000 |
June 1, 2017 |
Armstrong, Township of |
Replacement of roofing on Church Road Pumping Station Building |
$15,241 |
$7,621 |
June 1, 2017 |
Assiginack, Township of |
Water and Wastewater Rehabilitation, including Pump System, Chemical Feed Systems, Instrumentation Equipment, Distribution System, Sewage System and General Building Maintenance and Equipment |
$58,775 |
$29,388 |
March 1, 2017 |
Atikokan, Town of |
Rehabilitation of Sewage Pump Station 5 located at 59 Maple Cres in the Town of Atikokan by making upgrades to Sewage Pump Station # 5 |
$208,237 |
$104,119 |
January 1, 2017 |
Baldwin, Township of |
Slope Excavation, Application of Geosynthetic Clay Liner, Regrading of the Failing Berm as well as required Engineering at the Baldwin Township Exfiltrating Lagoon |
$50,000 |
$25,000 |
May 15, 2017 |
Black River-Matheson, Township of |
Upgrade Programmable Logic Controller (PLC) |
$50,000 |
$25,000 |
August 1, 2017 |
Bruce Mines, Town of |
Conduct a Study and Videography (camera) of the Town's Wastewater Collection System |
$5,200 |
$2,600 |
April 1, 2017 |
Bruce Mines, Town of |
Installation of a new Aeration System for the treatment of high levels of THMs (Trihalomethanes) at the pumping station |
$25,000 |
$12,500 |
July 30, 2017 |
Callander, Municipality of |
Sewage system optimization study, planning and design. |
$71,314 |
$35,657 |
September 20, 2016 |
Casey, Township of |
Replacement and relocation of manhole to house the flow meter and replace the flow meter due to flooding. |
$50,000 |
$25,000 |
April 1, 2016 |
Chapple, Township of |
Upgrade to main outlet pipe from Chapple Lagoon |
$50,000 |
$25,000 |
July 15, 2017 |
Charlton and Dack, Municipality of |
Replacement and Installation of existing high lift pumps from 7.5 horsepower to 5 horsepower with variable frequency drives at 50 Agnes Street, Charlton. |
$20,500 |
$10,250 |
January 4, 2017 |
Charlton and Dack, Municipality of |
Purchase and Installation of Variable Frequency Drive control units at 50 Agnes Street, Charlton. |
$20,000 |
$10,000 |
January 4, 2017 |
Charlton and Dack, Municipality of |
Installation of a new 4 inch treated water flow meter at 50 Agnes Street, Charlton. |
$3,500 |
$1,750 |
January 4, 2017 |
Charlton and Dack, Municipality of |
Purchase and Install 2 of the 3 raw water low lift pumps at 50 Agnes Street, Charlton. |
$4,000 |
$2,000 |
January 4, 2017 |
Charlton and Dack, Municipality of |
Replacement of Blow off Valves throughout Distribution System at 50 Agnes Street, Charlton. |
$2,000 |
$1,000 |
January 4, 2017 |
Chisholm, Township of |
Replacement of a 1700mm diameter stormwater culvert on Wasing Road. |
$25,000 |
$12,500 |
July 2, 2017 |
Chisholm, Township of |
Replacement of a 2100mm diameter stormwater culvert on Maple Road. |
$25,000 |
$12,500 |
July 2, 2017 |
Cobalt, Town of |
Install a chlorine analyzer loop for proven contact time in distribution |
$50,000 |
$25,000 |
December 1, 2016 |
Cobalt, Town of |
Pumphouse Road Water Treatment Plant highlift pumps and variable frequency drive replacement |
$28,500 |
$14,250 |
December 1, 2016 |
Cobalt, Town of |
Cobalt Wetland Lagoon System Condition Assessment and Feasibility Study |
$15,000 |
$7,500 |
December 1, 2016 |
Cobalt, Town of |
Pumphouse Road Water Treatment Plant upgrades to Chart Recorder and Supervisory Control and Data Acquisition (SCADA) system |
$8,000 |
$4,000 |
April 30, 2016 |
Cobalt, Town of |
Pumphouse Road Water Treatment Plant Chlorination system replacement |
$10,000 |
$5,000 |
December 1, 2016 |
Cobalt, Town of |
Pumphouse Road Water Treatment Plant Backwash and Progress Valves replacement |
$20,000 |
$10,000 |
December 1, 2016 |
Cochrane, Corporation of the Town of |
Water Pollution Control Plant- Disinfection (Ecoli) and Preliminary Treatment (Headworks) Upgrades |
$346,907 |
$173,454 |
June 1, 2017 |
Coleman,The Corporation of the Township of |
Water Freezing Mitigation Project: Installation of three Bleeder Stations |
$47,500 |
$23,750 |
January 1, 2017 |
Dryden, City of |
Water Treatment Plant Condition Analysis/Report to determine New Build/Rehabilitation Options |
$35,000 |
$17,500 |
March 31, 2017 |
Dryden, City of |
Water Treatment Plant Multiple Turbidity Meter Upgrade |
$20,000 |
$10,000 |
March 31, 2017 |
Dryden, City of |
Multiple Structural Relining of Watermains under Canadian Pacific Railway Tracks/Yard at 5 locations |
$200,000 |
$100,000 |
May 15, 2017 |
Dryden, City of |
Structural Relining (Cure in Place) of Sanitary Sewers at 4 locations |
$212,500 |
$106,250 |
May 15, 2017 |
Dryden, City of |
Sanitary Sewer Manhole Relining at approximately at 18 Locations |
$30,000 |
$15,000 |
May 15, 2017 |
Dryden, City of |
Replacement of 600mm Corrugated Steel Pipe (CSP) Storm Sewer Pipe on Van Horne Avenue |
$50,000 |
$25,000 |
May 15, 2017 |
Dryden, City of |
Update 2004 Land Implementation Study for the Water, Sanitary, and Storm Water Systems |
$45,000 |
$22,500 |
March 31, 2017 |
Ear Falls, Township of |
Clarifier Rehabilitation at the Ear Falls Wastewater Treatment Plant |
$232,027 |
$116,014 |
February 1, 2017 |
East Ferris, Municipality of |
Replacement and upgrading of a 20 metre stormwater culvert and rehabilitation of 4.3km of stormwater collection and conveyance system. |
$50,000 |
$25,000 |
July 2, 2017 |
Elliot Lake, City of |
Repair of waste water pumping systems that services approximately 6000 homes due to failure at 2 Scott Road, Elliot Lake, Ontario. |
$198,743 |
$99,372 |
May 1, 2017 |
Emo, Township of |
Upgrade to the Main Sewage Pumping Station - Roy Street Sewage Lift/Pumping Station, including Pumps, Piping and Controls |
$87,122 |
$43,561 |
April 1, 2017 |
Emo, Township of |
Upgrade to Existing Water Treatment Plant Raw Water Low Lift Pumps |
$22,500 |
$11,250 |
April 1, 2017 |
Englehart, Town of |
Upgrade of the main electrical system at the First Street Waterplant |
$112,500 |
$56,250 |
May 1, 2017 |
Espanola, Town of |
Infrastructure Renewal Project Phase 2 for the rehabilitation of approximately 6.7 km of water, wastewater and stormwater infrastructure |
$364,106 |
$182,053 |
April 1, 2017 |
Evanturel, Township of |
Water Servicing Options Study |
$50,000 |
$25,000 |
September 30, 2016 |
Fauquier-Strickland, Township of |
Replace existing 8.5 HP raw water low lift pump |
$8,105 |
$4,052 |
March 6, 2017 |
Fauquier-Strickland, Township of |
Replace existing 7.5 HP high lift pump with new Variable Frequency Drive (VFD) |
$18,236 |
$9,118 |
March 6, 2017 |
Fauquier-Strickland, Township of |
Structural New Construction - Water Plant Backwash surge tank |
$22,513 |
$11,257 |
February 6, 2017 |
Fauquier-Strickland, Township of |
Water Plant Chemical Resistant Exhaust Fan equipment upgrade |
$1,146 |
$573 |
February 6, 2017 |
Fort Frances, Town of |
Replacement of water main, sanitary sewer mains and associated service lines along 2nd Street East from Mowat Avenue to Portage Avenue |
$638,506 |
$319,253 |
October 25, 2016 |
French River, Municipality of |
Assessment of Noelville Wastewater/Stormwater Infrastructure Upgrades |
$50,000 |
$25,000 |
March 1, 2017 |
Gillies, The Township of |
Rehabilitation of Multiple Stormwater Assets within the Township including Ditch Excavation and the Upsizing of Culverts |
$50,000 |
$25,000 |
May 1, 2017 |
Gore Bay, Town of |
Replacement of 150m of Eleanor Street Watermain - From Phipps Street to Laird Street |
$106,066 |
$53,033 |
April 3, 2017 |
Greenstone, Municipality of |
Geraldton Ward Waterline Rehabilitation Phase III |
$230,902 |
$115,451 |
May 1, 2017 |
Greenstone, Municipality of |
Longlac Ward Albany Place Watermain Replacement |
$24,269 |
$12,134 |
May 1, 2017 |
Hearst, Town of |
Replace three (3) low-lift pumps at the Hearst Water Treatment Plant with new energy efficient pumps equipped with Variable Frequency Drives |
$42,895 |
$21,448 |
September 4, 2017 |
Hearst, Town of |
Installation of Ultraviolet (UV-254) technology to monitor the efficiency of the process removing organic matter at Hearst's Water Treatment Plant |
$27,500 |
$13,750 |
June 5, 2017 |
Hearst, Town of |
Re-roofing of fifth Street Pumping Station Building |
$7,500 |
$3,750 |
June 5, 2017 |
Hearst, Town of |
Addition of Backflow Preventers at Fifth Street Sewage Pumping Station |
$10,000 |
$5,000 |
June 5, 2017 |
Hilton Beach, Village of |
Equipment Upgrades at the Water Treatment Plant for Chlorine analyzer, Turbidity meter and singer valve. |
$7,500 |
$3,750 |
June 1, 2017 |
Hilton Beach, Village of |
Blower, rotating biological contactor Pump and Lift Station Pump installation |
$22,500 |
$11,250 |
May 1, 2017 |
Hilton Beach, Village of |
Installation of new 15 horsepower Primary Well Pump |
$6,100 |
$3,050 |
July 1, 2017 |
Hilton Beach, Village of |
Upgrades to components of the Supervisory Control and Data Acquisition (SCADA) at the Wastewater Plant |
$9,556 |
$4,778 |
March 1, 2017 |
Hornepayne, Township of |
Variable Frequency Drive for 3 High Lifts at the Water Treatment Plant |
$25,000 |
$12,500 |
January 1, 2017 |
Hornepayne, Township of |
Replace 15 Main Valves Within the Water Distribution System |
$100,000 |
$50,000 |
June 1, 2017 |
Hornepayne, Township of |
Repair/Replace 20 Curb Stops Within the Water Distribution System |
$32,875 |
$16,438 |
July 1, 2017 |
Hornepayne, Township of |
Radio Communication System for Raw Water Pumping Station |
$5,000 |
$2,500 |
May 1, 2017 |
Huron Shores, Municipality of |
Storm sewer rehabilitation from the end of Phase II, east along John Street and north along Chiblow Lake Road |
$50,000 |
$25,000 |
June 1, 2017 |
Ignace, Township of |
Sewer Main upgrade, with replacement of asbestos pipe to new 200 mm Polyvinyl chloride (PVC) main and storm sewer main |
$134,669 |
$67,335 |
August 21, 2017 |
Ignace, Township of |
Sewer Main upgrade, with replacement of one sewer main approximately 170 meters long and replacement of one sewer main approximately 50 meters long |
$123,484 |
$61,742 |
August 21, 2017 |
James, Township of |
Enhance programmable logic controller (PLC) at the water treatment plant. Located at the Elk Lake water Treatment plant, 4 First Street which serves 245 houses |
$11,200 |
$5,600 |
March 1, 2017 |
James, Township of |
Purchase new well level probe for main well for the township which serves 440 residents and 160 service connections. Located at the Elk Lake Water Treatment plant, 4 First Street. |
$2,035 |
$1,018 |
March 1, 2017 |
James, Township of |
Repair programmable logic controller (PLC) at the water treatment plant. Located at the Elk Lake water Treatment plant, 4 First Street which serves 440 residents and 160 service connections. |
$6,100 |
$3,050 |
March 1, 2017 |
Johnson, Township of |
Upgrade the Johnson Township Water Treatment Plant |
$50,000 |
$25,000 |
April 30, 2017 |
Kapuskasing, Town of |
Upgrade to sanitary forcemain and relocation of the Mill Street forcemain |
$501,015 |
$250,508 |
May 15, 2017 |
Kearney, Town of |
Drilled well/water system at 111 Main Street. Upgrading of water system from lake source water supply to drilled well for human consumption/use |
$7,500 |
$3,750 |
May 6, 2017 |
Kearney, Town of |
Drilled well/water system at 163 Main Street. Upgrading of water system from lake source water supply to drilled well for human consumption/use |
$7,500 |
$3,750 |
May 7, 2017 |
Kearney, Town of |
Rehabilitate Septic System at 111 Main Street |
$18,833 |
$9,417 |
June 1, 2017 |
Kearney, Town of |
Rehabilitate Septic System at 163 Main Street |
$16,166 |
$8,083 |
June 1, 2017 |
Kenora, City of |
First Street South at Main Street South Storm Sewer Relining |
$26,890 |
$13,445 |
November 1, 2017 |
Kenora, City of |
Houghton Road Storm Sewer Relining |
$196,010 |
$98,005 |
November 1, 2017 |
Kenora, City of |
Valley Drive Sanitary Sewer Relining |
$148,366 |
$74,183 |
May 1, 2017 |
Kenora, City of |
Drewry Drive Sanitary Sewer Relining |
$60,313 |
$30,156 |
May 1, 2017 |
Kenora, City of |
Gunne Crescent Sanitary Sewer Relining |
$30,957 |
$15,478 |
May 1, 2017 |
Kenora, City of |
Seegmiller Avenue Sanitary Sewer Relining |
$9,284 |
$4,642 |
May 1, 2017 |
Kenora, City of |
Nairn Avenue Sanitary Sewer Relining |
$20,713 |
$10,357 |
May 1, 2017 |
Kenora, City of |
Heenan Place Sanitary Sewer Relining - East End |
$24,332 |
$12,166 |
May 1, 2017 |
Kenora, City of |
Heenan Place Sanitary Sewer Relining - Narin Westerly |
$5,241 |
$2,620 |
May 1, 2017 |
Kenora, City of |
Ninth Avenue South #345 to #322 Sanitary Sewer Relining |
$9,982 |
$4,991 |
May 1, 2017 |
Kenora, City of |
First Street North West Dead End Sanitary Sewer Relining |
$11,230 |
$5,615 |
May 1, 2017 |
Kenora, City of |
Ninth Street North Storm Sewer Partial Replacement |
$24,750 |
$12,375 |
May 1, 2017 |
Killarney, Municipality of |
Conduct a survey and inspection of the Sewage Collection System to develop a work plan/tender package for required upgrades/repairs. |
$61,904 |
$30,952 |
May 15, 2017 |
Larder Lake, Township of |
Raw sewage pump preplacement and soft start installation for the waste water treatment plant. |
$40,981 |
$20,491 |
November 1, 2016 |
Larder Lake, Township of |
Supervisory Control and Data Acquisition (SCADA) system replacement and enhancements for the water treatment plant |
$22,500 |
$11,250 |
October 1, 2016 |
Latchford, Town of |
Replace and reprogram computer software that runs Water Treatment Plant |
$35,000 |
$17,500 |
February 1, 2017 |
Latchford, Town of |
Electrical upgrades to lift station |
$15,000 |
$7,500 |
May 1, 2017 |
Macdonald, Meredith and Aberdeen Additional, Township of |
Rehabilitation of sanitary sewage system components including the Supervisory Control and Data Acquisition system (SCADA) and controls at two sewage lift stations, sewage pumps and valves. |
$47,438 |
$23,719 |
January 1, 2017 |
Macdonald, Meredith and Aberdeen Additional, Township of |
Rehabilitation of Drinking Water Supply and Treatment System Components |
$54,697 |
$27,348 |
January 1, 2017 |
Machar, Township of |
Replace culverts and raise the grade of Leighton Road at various locations to mitigate flooding, washouts and erosion from spring flooding and high storm events |
$50,000 |
$25,000 |
April 1, 2017 |
Machin, Municipality of |
Vermilion Bay Water Treatment Plant, 8 Bay Street, Vermilion Bay Ontario. System control and Data acquisition upgrading serving 218 services or approximately 550 people. |
$67,834 |
$33,917 |
December 12, 2016 |
Manitouwadge, Township of |
The rehabilitation of town wells #3 & #4 located at 41A Ohsweken Road |
$42,500 |
$21,250 |
May 1, 2017 |
Marathon, Town of |
Replace Clarifier Domes |
$103,934 |
$51,967 |
March 1, 2017 |
Marathon, Town of |
Purchase and Install Turbo Blower (with Programmable Logic Controller (PLC) and Supervisory Control and Data Acquisition (SCADA) system) |
$58,027 |
$29,014 |
February 1, 2017 |
Markstay-Warren, Municipality of |
Design and construct a new Stormwater Outlet (surge capacity) |
$37,500 |
$18,750 |
April 1, 2017 |
Markstay-Warren, Municipality of |
Increasing Warren Sewage Lift Station reliability by replacing two aging 10 horsepower lift pumps |
$12,500 |
$6,250 |
April 1, 2017 |
Matachewan, The Corporation of the Township of |
Upgrades to the Matachewan Storm Water Control System located in an area covering 10 municipal streets between Calbeck Avenue and Helen Avenue |
$50,000 |
$25,000 |
May 1, 2017 |
Mattawa, Town of |
Water Treatment Plant Chlorination Analysis Improvements |
$18,750 |
$9,375 |
May 1, 2017 |
Mattawa, Town of |
Water Storage Reservoir : Upgrades to Emergency Backup Power, Supervisory Control and Data Acquisition Communication, Corroded Piping, Valves, Access Hatches, and Access Road |
$88,250 |
$44,125 |
May 1, 2017 |
Mattice - Val Côté, Municipality of |
Repairs to low-lift water pumping station building |
$8,500 |
$4,250 |
March 1, 2017 |
Mattice - Val Côté, Municipality of |
Install Variable Frequency Drives (VFD) on water treatment plant high-lift pumps |
$17,000 |
$8,500 |
March 1, 2017 |
Mattice - Val Côté, Municipality of |
Replace one of the sanitary pumps at the Sewage pumping station |
$13,500 |
$6,750 |
March 1, 2017 |
Mattice - Val Côté, Municipality of |
Replace both sanitary pump seats at the Sewage pumping station |
$11,000 |
$5,500 |
March 1, 2017 |
McKellar, Township of |
Blackwater Bridge replacement with outflow stormdrain culvert |
$50,000 |
$25,000 |
June 1, 2016 |
Moosonee, Town of |
Water Valve Rehabilitation for Directional Flushing Program |
$149,785 |
$74,893 |
July 1, 2017 |
Nairn and Hyman, Township of |
Replacement of corroded soda ash tank system with a new poly tank and stainless feeder at the Nairn Centre Water Treatment Plant |
$6,225 |
$3,113 |
April 1, 2017 |
Nairn and Hyman, Township of |
Improve water quality at the dead end on McIntyre Street by installing flushing capacity |
$5,275 |
$2,638 |
June 1, 2017 |
Nairn and Hyman, Township of |
Replace filter media from both filters, repair under drains, install new media and replace faulty valves at the Nairn Centre Water Treatment Plant |
$12,665 |
$6,333 |
January 3, 2018 |
Nairn and Hyman, Township of |
Swab complete distribution to remove biofilm buildup on pipes and sediment in pipes in the town of Nairn Centre |
$11,250 |
$5,625 |
September 1, 2017 |
Neebing, Municipality of |
Belanger Rd Culvert Rehabilitation |
$5,743 |
$2,872 |
June 1, 2017 |
Neebing, Municipality of |
Jarvis Bay Rd Culvert Rehabilitation |
$8,489 |
$4,244 |
June 1, 2017 |
Neebing, Municipality of |
Lesnick Road Culvert Rehabilitation |
$8,475 |
$4,237 |
June 1, 2017 |
Neebing, Municipality of |
Union School Road Culvert Rehabilitation |
$9,568 |
$4,784 |
June 1, 2017 |
Neebing, Municipality of |
Larson Road Culvert Rehabilitation |
$9,847 |
$4,924 |
June 1, 2017 |
Neebing, Municipality of |
Margaret Street Culvert Rehabilitation |
$6,346 |
$3,173 |
June 1, 2017 |
Neebing, Municipality of |
Walker Road Culvert Rehabilitation |
$1,532 |
$766 |
June 1, 2017 |
Nipigon, Township of |
Upgrade to existing storm water infrastructure with a new Rain Garden to improve quality of storm water discharge. |
$20,000 |
$10,000 |
June 1, 2017 |
Nipigon, Township of |
Restoration of existing storm sewer collection system, manhole, catch basins and storm sewer pipe. |
$104,648 |
$52,324 |
July 3, 2017 |
North Bay, City of |
Extension of water and sanitary services to the Cedar Heights area. |
$2,287,004 |
$1,143,502 |
April 1, 2017 |
Northeastern Manitoulin and the Islands, Town of |
Relocation and Replacement of Membrane Programmable Logic Controller (PLC) at the Little Current Water Treatment Plant |
$50,000 |
$21,000 |
May 1, 2017 |
Northeastern Manitoulin and the Islands, Town of |
Rehabilitation of Generator and Transfer Switch at the Little Current Main Pump House |
$15,000 |
$10,000 |
June 1, 2016 |
Northeastern Manitoulin and the Islands, Town of |
Highlift Pump Rehabilitation at the Sheguiandah Water Treatment Plant |
$10,498 |
$6,749 |
March 1, 2017 |
O'Connor, Township of |
Township Wide Stormwater Culvert Replacements of Approximately 62 |
$50,000 |
$25,000 |
May 1, 2017 |
Oliver Paipoonge, Municipality of |
Environmental Assessment Study and Replacement of Rosslyn Municipal Wells North and South |
$50,000 |
$25,000 |
February 1, 2017 |
Opasatika,Township of |
Interconnectivity valve replacement between clear wells |
$5,000 |
$2,500 |
February 1, 2017 |
Opasatika,Township of |
Optimize green sand filter and diffusers |
$10,000 |
$5,000 |
February 1, 2017 |
Opasatika,Township of |
Repair 7 hydrants in township to improve water distribution system effectiveness. |
$25,000 |
$12,500 |
February 1, 2017 |
Opasatika,Township of |
Repair and replace five curb valves to improve the water distribution system |
$4,000 |
$2,000 |
February 1, 2017 |
Opasatika,Township of |
Repair main sewage pump house building |
$6,000 |
$3,000 |
February 1, 2017 |
Papineau-Cameron,Township of |
Multiple Stormwater control systems Rehabilitation of structural upgrades/restoration, and replacement of multiple stormwater culverts |
$50,000 |
$25,000 |
June 1, 2016 |
Parry Sound, Town of |
Replace and upsize all watermains on Waubeek Street |
$96,976 |
$48,488 |
May 1, 2017 |
Parry Sound, Town of |
Replace failed storm sewer on Waubeek Street |
$96,976 |
$48,488 |
May 1, 2017 |
Parry Sound, Town of |
Complete replacement of failed sanitary sewer on Waubeek Street |
$96,976 |
$48,488 |
May 1, 2017 |
Parry Sound, Town of |
Complete replacement of leaking and aged sanitary forcemeain on Waubeek Street |
$96,976 |
$48,488 |
May 1, 2017 |
Parry Sound, Town of |
Replace and upsize all watermains on Prospect Street |
$96,976 |
$48,488 |
May 1, 2017 |
Parry Sound, Town of |
Replace leaking and aged storm sewer on Prospect Street |
$96,976 |
$48,488 |
May 1, 2017 |
Parry Sound, Town of |
Complete replacement of leaking and failing sanitary sewer on Prospect Street |
$96,976 |
$48,488 |
May 1, 2017 |
Parry Sound, Town of |
Complete replacement of leaking and aged sanitary forcemeain on Prospect Street |
$96,976 |
$48,488 |
May 1, 2017 |
Petawawa, Town of |
Upgrade existing watermain on Mary Street to 300mm diameter line |
$273,249 |
$136,625 |
May 1, 2017 |
Pickle Lake, Township of |
Sewage Clarifier Rehabilitation, tank rake-paddle installation (Cat Lake Road) |
$44,275 |
$22,138 |
May 1, 2017 |
Pickle Lake, Township of |
Broken hydrant replacement near 1 Koval Street and upgrading approximately 30 meters of water main to prevent future freeze-ups. |
$19,074 |
$9,537 |
May 6, 2017 |
Plummer Additional, Township of |
Plummer Road Drainage and Erosion Improvements; install 750mm x 18m stormwater culvert along 300 metres of Plummer Road |
$50,000 |
$25,000 |
March 1, 2017 |
Powassan, The Corporation of the Municipality of |
Rehabilitation - Cured-in-place pipe Relining at 250 Clark Street - community hub |
$16,500 |
$8,250 |
May 1, 2017 |
Powassan, The Corporation of the Municipality of |
New pump for Sewage Lift Station #1 at 288 Clark Street to replace old worn pump |
$9,000 |
$4,500 |
April 3, 2017 |
Powassan, The Corporation of the Municipality of |
Rehabilitation of the wastewater pipe at 74 Queens Ave |
$2,500 |
$1,250 |
June 12, 2017 |
Powassan, The Corporation of the Municipality of |
Wastewater pipe rehabilitation at 327 Edward Street |
$2,500 |
$1,250 |
August 1, 2017 |
Powassan, The Corporation of the Municipality of |
Upgrade/replacement of chlorine analyzer for water pumping station at 76 Fairview Lane |
$3,000 |
$1,500 |
May 1, 2017 |
Powassan, The Corporation of the Municipality of |
Flow Meter replacement for sewage lift station #2 at 76 HWY 534 |
$5,000 |
$2,500 |
June 1, 2017 |
Powassan, The Corporation of the Municipality of |
Upgrade pump at Sewage Lift Station #2 at 76 HWY 534 which services over 1/3 of the wastewater services in the municipality |
$4,000 |
$2,000 |
May 15, 2017 |
Rainy River, Town of |
Water Line and Sanitary Sewer Line Replacement - 100-500 Atwood Avenue serving 20 residential and commercial buildings |
$151,580 |
$75,790 |
July 15, 2016 |
Red Rock, Township of |
Upgrade to Water Storage Tank Liner - Water Treatment plant |
$53,911 |
$26,956 |
June 1, 2017 |
Redditt LSB |
Connection of secondary water distribution lines from the Redditt water system to 44 local residents' homes. |
$50,000 |
$25,000 |
August 21, 2017 |
Sables-Spanish Rivers, Township |
Rehabilitation Project involving the Relining of Water Storage Tower that supports the Water Treatment System serving 500 Customers |
$50,000 |
$25,000 |
May 1, 2017 |
Schreiber, Township of |
Feasibility and detailed design for an elevated drinking water storage tank. |
$98,007 |
$49,004 |
May 1, 2016 |
Sioux Lookout, Municipality of |
Queen Street Water and Sanitary Infrastructure Restoration |
$317,000 |
$158,500 |
April 1, 2017 |
Smooth Rock Falls, Town of |
Replacement of existing 450 mm sanitary sewer at Fourth Street to Hollywood Avenue / Sixth Street intersection |
$136,106 |
$68,053 |
October 28, 2016 |
Spanish, The Corporation of the Town of |
Interior Lining Replacement at Elevated Tank |
$81,464 |
$40,732 |
May 1, 2017 |
St. Joseph, Township of |
Rehabilitation of Drinking Water Supply and Treatment System Components including well pump, high lift pumps, fire pump and analytical equipment. |
$50,000 |
$25,000 |
January 1, 2017 |
St.-Charles, Corporation of the Municipality of |
St.-Charles lagoon waste water flowmeter project. |
$11,250 |
$5,625 |
May 15, 2017 |
Tehkummah, Township of |
Supervisory Control and Data Acquisition (SCADA) System Purchase and Installation |
$50,608 |
$25,304 |
May 1, 2017 |
Temiskaming Shores, City of |
Replacement of Existing Iron Removal Filters at the McCamus Avenue Water Treatment Plant. |
$344,282 |
$172,141 |
May 1, 2017 |
Terrace Bay, Township of |
Replacement of Lakeview Dr. & Kenogami Rd. Sanitary Sewage Outfall |
$166,101 |
$83,051 |
March 1, 2017 |
Thessalon, Town of |
River Street Storm Sewer Rehabilitation |
$60,000 |
$30,000 |
April 1, 2017 |
Thessalon, Town of |
Main Street and Mill Lane Storm Sewer Installation |
$50,000 |
$25,000 |
April 1, 2017 |
Thessalon, Town of |
Feasibility Study, Hydraulic Analysis, Geotechnical Assessment and Environmental Assessment for a Water Storage Facility |
$44,739 |
$22,370 |
March 1, 2017 |
Thorne, Local Service Board |
Thorne Water Treatment Plant Capital Improvements |
$50,000 |
$25,000 |
January 1, 2017 |
Thornloe, Village of |
Upgrading of perimeter Safety and Security Fencing to Wastewater Lagoon |
$12,500 |
$6,250 |
July 1, 2017 |
Thornloe, Village of |
Upgrade of Flow Meter Installation and Construction of a Protective Insulated Building |
$10,000 |
$5,000 |
July 1, 2017 |
Thunder Bay, City of |
Drainage improvements and Low Impact Development at Birch Point and Jumbo Gardens |
$163,500 |
$81,750 |
June 1, 2017 |
Thunder Bay, City of |
Construction of a 1200mm Storm Sewer from the McIntyre River to Balmoral St and north to John St |
$202,500 |
$101,250 |
June 1, 2017 |
Thunder Bay, City of |
Extension of Catch Basins in Multiple Locations to Improve Local Drainage |
$25,000 |
$12,500 |
June 1, 2017 |
Thunder Bay, City of |
Post Assessment Repairs to Stormwater Outfalls |
$12,500 |
$6,250 |
June 1, 2017 |
Thunder Bay, City of |
Construction of a 375mm Storm Sewer on Burris Street - Margaret Street to 100 m N - to Address Local Surface Drainage Issues |
$35,000 |
$17,500 |
June 1, 2017 |
Thunder Bay, City of |
Storm Sewer Replacement on Egan Street - Algoma Street to Garrard Street |
$25,000 |
$12,500 |
June 1, 2017 |
Thunder Bay, City of |
Storm Sewer Installation on Crescent Avenue - Cox Crescent to 80 m N |
$20,000 |
$10,000 |
June 1, 2017 |
Thunder Bay, City of |
600 mm Storm Sewer Installation on Frederica Street - W Neebing to Dead End |
$160,000 |
$80,000 |
June 1, 2017 |
Thunder Bay, City of |
Conducting of Hydraulic Engineering Drainage Study in the Intercity Area |
$312,500 |
$156,250 |
June 1, 2017 |
Thunder Bay, City of |
Construction of a 300 mm Relief Storm Sewer on Prospect Avenue |
$25,000 |
$12,500 |
June 1, 2017 |
Thunder Bay, City of |
Lyon Ditch Drainage Improvements including Increased Capacity |
$50,000 |
$25,000 |
June 1, 2017 |
Thunder Bay, City of |
Construction of 1200mm Twin Relief Storm Sewer and Outfall at James Street - Neebing River to Churchill Drive |
$500,000 |
$250,000 |
June 1, 2017 |
Thunder Bay, City of |
Construction of 1500mm Stormwater Outfall at James Street - Neebing River to Riverview Drive |
$125,000 |
$62,500 |
June 1, 2017 |
Thunder Bay, City of |
Construction of a 450-525 mm Relief Storm Sewer from McGill Crescent to the Dalhousie / McMaster St. Area |
$125,000 |
$62,500 |
June 1, 2017 |
Thunder Bay, City of |
City-Wide Stormwater Infrastructure Inventory and Condition Assessment |
$125,000 |
$62,500 |
June 1, 2017 |
Thunder Bay, City of |
First Avenue Drainage Improvements including Design and Construction of 150m of Storm Sewer |
$50,000 |
$25,000 |
June 1, 2017 |
Thunder Bay, City of |
Design of Comprehensive Surface/Stormwater Management Plan for the Solid Waste and Recycling Facility |
$75,000 |
$37,500 |
June 1, 2017 |
Thunder Bay, City of |
Construction of 300 mm Sanitary Sewer Separation on Archibald Street: Dease Street to Leith Street |
$387,500 |
$193,750 |
June 1, 2017 |
Thunder Bay, City of |
Replacement of 250 mm Sanitary Sewer on Court Street: John Street to Bay Street |
$325,000 |
$162,500 |
June 1, 2017 |
Thunder Bay, City of |
Replacement of Sanitary Sewer connections on First Avenue: Memorial Avenue to Fort William Road |
$50,000 |
$25,000 |
June 1, 2017 |
Thunder Bay, City of |
Construction of 375-450mm Stormwater Separation Sewer on Selkirk Street - Arthur Street to Cuthbertson Place and Cuthbertson Place - Selkirk St to Franklin St. |
$63,250 |
$31,625 |
June 1, 2017 |
Thunder Bay, City of |
Construction of 525 mm Sanitary Separation Sewer on Brodie Street - Neebing River to Dease Street |
$360,800 |
$180,400 |
June 1, 2017 |
Thunder Bay, City of |
Construction of 450mm Stormwater Separation Sewer on Murray Avenue - Franklin Street to Selkirk Street |
$115,500 |
$57,750 |
June 1, 2017 |
Thunder Bay, City of |
Construction of 450mm Stormwater Separation Sewer on Isabella Street - Franklin Street to Selkirk Street |
$115,467 |
$57,733 |
June 1, 2017 |
Thunder Bay, City of |
Construction of a 300mm Stormwater Separation Sewer on McGillivray Street |
$22,000 |
$11,000 |
June 1, 2017 |
Thunder Bay, City of |
Cement Mortar Lining of 150mm Cast Iron Watermains in the Hallam Street/Dewe Avenue/Dacre Street/Hodder Avenue Grid |
$369,847 |
$178,924 |
June 1, 2017 |
Thunder Bay, City of |
Replacement of Existing 150mm Cast Iron Watermain on Court Street - John Street to Bay Street |
$352,500 |
$176,250 |
June 1, 2017 |
Thunder Bay, City of |
Replacement of Existing 525 mm Ductile Iron Watermain on First Ave - Memorial Avenue to Fort William Road, and Winnipeg Avenue from First Avenue to Beverly Street |
$417,500 |
$208,750 |
June 1, 2017 |
Thunder Bay, City of |
Hilldale Rd/ Trendiak Rd Culvert Replacement Program |
$50,000 |
$25,000 |
June 1, 2017 |
Thunder Bay, City of |
Construction of Low Impact Development Stormwater Management Facilities in the McVicar Creek Basin |
$14,000 |
$13,000 |
June 1, 2017 |
Thunder Bay, City of |
Design and Construction of up to ten (10) Low Impact Development Stormwater Management Facilities |
$712,500 |
$356,250 |
June 1, 2017 |
Thunder Bay, City of |
Construct Low Impact Development Stormwater Management Facility within George Burke Park |
$50,000 |
$25,000 |
June 1, 2017 |
Thunder Bay, City of |
Sandy Beach Road Ditch Upgrade and Deepening |
$25,000 |
$12,500 |
June 1, 2017 |
Thunder Bay, City of |
Highgate Road Drainage Improvements including Design and Construction |
$75,000 |
$37,500 |
June 1, 2017 |
Wawa, Municipality of |
Water Reservoir Rehabilitation and technical / operational rebuild (Michipicoten River Village) |
$95,000 |
$47,500 |
April 1, 2017 |
Wawa, Municipality of |
Water Reservoir Dechlorinator. Purchase and installation of new equipment (Michipicoten River Village) |
$100,000 |
$50,000 |
January 1, 2017 |
Wawa, Municipality of |
Study to identify actions necessary to address Trihalomethane in drinking water |
$74,318 |
$37,159 |
May 1, 2017 |
West Nipissing, Municipality of |
Relocation of shut off valve at Water Treatment Plant on Nipissing Street, Sturgeon Falls |
$7,500 |
$3,750 |
February 1, 2017 |
West Nipissing, Municipality of |
Structural upgrade to wastewater forcemain at Holditch Street extension |
$150,000 |
$75,000 |
May 1, 2017 |
West Nipissing, Municipality of |
Structural extension of water services to complete loop on Railway Street |
$50,000 |
$25,000 |
May 1, 2017 |
West Nipissing, Municipality of |
Replacement of Main Street watermains |
$25,000 |
$12,500 |
May 1, 2017 |
West Nipissing, Municipality of |
Replacement and Extension of Ramsay Street water main |
$25,000 |
$12,500 |
May 1, 2017 |
West Nipissing, Municipality of |
Structural upgrade of Sand Hill area water services |
$125,000 |
$62,500 |
May 1, 2017 |
West Nipissing, Municipality of |
Enhancement of Sabourin Road water services |
$50,000 |
$25,000 |
May 1, 2017 |
West Nipissing, Municipality of |
Extension of Bay Street water services to industrial park |
$50,000 |
$25,000 |
May 1, 2017 |
West Nipissing, Municipality of |
Upgrade of brick manholes in numerous locations throughout Sturgeon Falls |
$24,375 |
$12,188 |
May 1, 2017 |
White River, Township of |
Replacement of Waste Water Sewer Main Line (forcemain) from Ontario Street pumping station approximately. |
$165,240 |
$82,620 |
June 1, 2017 |
Associated links
Government of Canada's $180-billion+ infrastructure plan in Budget 2017
Federal infrastructure investments in Ontario
The Clean Water and Wastewater Fund
Build ON 2017 Infrastructure Update
Twitter: @INFC_eng
Web: Infrastructure Canada
SOURCE Infrastructure Canada
Brook Simpson, Press Secretary, Office of the Minister of Infrastructure and Communities, 613-219-0149, [email protected]; Craig MacBride, Media Contact, Government of Ontario, 416-212-0453, [email protected]; Stacey Levanen, Supervisor - Corporate Communications, City of Thunder Bay, 807-625-3650, [email protected]; Infrastructure Canada, 613-960-9251, Toll free: 1-877-250-7154, Email: [email protected],
Also from this source
Share this article