Blue Note Mining and First Gold Exploration announce positive prefeasibility
study for the Croinor gold project
MONTREAL, July 15 /CNW Telbec/ - Blue Note Mining Inc. (TSXV: BNT) ("Blue Note") and First Gold Exploration Inc. (TSXV: EFG) ("First Gold") are pleased to report positive results from the Prefeasibility Study (the "Study") for their jointly owned Croinor gold project located near Val-d'Or, Quebec. The Study confirms the project's robust economics and excellent potential for long term growth through a focused exploration program. The Study was completed by InnovExplo Inc. with the participation and contribution of Golder Associates and other contractors, consultants and suppliers.
The Study indicates that the Croinor gold project has a 97% internal rate of return using Bloomberg consensus gold prices and exchange rates for 2011 through to 2015.* It outlines an underground mining operation using custom milling at a fully permitted milling facility near Val-d'Or and displays significant improvements over the Preliminary Economic Assessment prepared by Golder Associates filed in July 2009 including more than doubling the mine production.
The Technical Report in accordance with Regulation 43-101 for the Prefeasibility Study will be filed on www.sedar.com within 45 days of this news release. Highlights from the Study are presented in the following table. All currency in this report is in Canadian dollars unless otherwise noted.
HIGHLIGHTS OF PREFEASIBILITY STUDY
------------------------------------------------------------------------- Parameters Results ------------------------------------------------------------------------- ------------------------------------------------------------------------- Proven & probable mineral reserve 689,829 tonnes at 8.35g/t ------------------------------------------------------------------------- Total contained gold reserve 185,260 oz ------------------------------------------------------------------------- Mine life (including 14-month preproduction) 5 years ------------------------------------------------------------------------- Daily mine production 500 tonnes per day ------------------------------------------------------------------------- Gold recovery 97.5% ------------------------------------------------------------------------- Annual gold production 39,181 to 45,631 oz ------------------------------------------------------------------------- LOM recovered gold 170,556 oz ------------------------------------------------------------------------- Average cash operating cost $160/tonne ------------------------------------------------------------------------- Average cash operating cost US$572/oz ------------------------------------------------------------------------- Capital cost (including $7.4M sustaining/ working capital) $ 26 million * ------------------------------------------------------------------------- Total cost per ounce US$715/oz ------------------------------------------------------------------------- Total revenue $182 million ------------------------------------------------------------------------- Total operating cost $104 million ------------------------------------------------------------------------- Total project cost $130 million ------------------------------------------------------------------------- Total operating cash flow (before tax & royalties) $52.4 million ------------------------------------------------------------------------- Net cash flow (pretax after royalties) $47.4 million ------------------------------------------------------------------------- NPV (pretax @ 7% discount ) $35.9 million ------------------------------------------------------------------------- IRR (pretax) 97% ------------------------------------------------------------------------- Payback period 25 months ------------------------------------------------------------------------- Pre-production period (including 42,000t of production) 14 months ------------------------------------------------------------------------- *Includes capitalized preproduction operating cost net of associated revenue *Bloomberg base case consensus forecasts: 2011 to 2015 ----------------------------- Gold Price ($US/oz) 1,178; 1,165; 1,123; 850; 850 Exchange Rate ($C/$US) 1.04/1.06/1.09/1.05/1.05
"We are very pleased with the results of the Prefeasibility Study which substantiates the quality of the Croinor gold project," commented Leon Methot, Blue Note's Chairman and Chief Executive Officer. "The present reserve base is an excellent starting point for the project and can be significantly expanded by upgrading the resource through a combination of infill and deep exploration drilling. We are progressing well with the permitting process and will continue to work expediently to bring this robust project into production."
"I'm very pleased that our project is now ready for development with 185,000 ounces of reserves, a short payback period and a whopping 97% IRR. The future cash flows of the project will greatly benefit both Blue Note and First Gold Exploration.", comments Eric Leboeuf, President and Chief Executive Officer of First Gold Exploration."
Project Overview
The Croinor gold deposit located approximately 70 km from Val-d'Or, Quebec, consists of 38 high grade gold bearing quartz veins and remains open at depth. Recent production from the deposit totaled 8,081 ounces in three phases from two separate open pits from November 2003 to May 2005. The material was processed at a nearby Val-d'Or milling facility.
Gold mineralization is essentially associated with metasomatic pyrite located in quartz vein walls as well as in the strongly altered host-rock material of tectonic breccia. Gold occurs as inclusions within and along the edges of pyrite grains. Minor amounts of chalcopyrite and pyrrhotite are sometimes present with the pyrite. Occasionally, free gold is found within quartz veins of shear zones as well as in their strongly metasomatized walls.
Resource Estimation
After the open pit operations ceased in May 2005, two Mineral Resource estimates were completed for the Croinor gold project. The first was prepared in November 2005 by Carl Pelletier of InnovExplo Inc. and was entitled "NI 43-101 Technical Report for the Mineral Resource Estimate of the Croinor gold project". This formed the basis of the July 2009 Preliminary Economic Assessment by Francois Chabot of Golder Associates (the "PEA"). The second, prepared by Pierre O'Dowd in September 2009 entitled "NI 43-101 Resource Estimate Update and 2008 Technical Report on the Croinor 1 and 2 Projects", incorporated a 12,648-meter drill program conducted from 2007 to 2009. The latter forms the basis of the current Study.
Following is the Mineral Resource summary:
------------------------------------------------------------------------- Mineral Resource Estimate ------------------------------------------------------------------------- Measured and Indicated Resource ------------------------------------------------------------------------- Category Cut-off 5 g/t Au Cut-off 7g/t Au -------------------------------------------------------------- tonnes g/tonne ounces tonnes g/tonne ounces ------------------------------------------------------------------------- Measured 31,192 8.59 8,615 15,210 12.46 6,092 ------------------------------------------------------------------------- Indicated 783,036 9.13 229,799 385,636 12.70 157,416 ------------------------------------------------------------------------- ------------------------------------------------------------------------- Total Resource 814,228 9.11 238,414 400,846 12.69 163,508 -------------------------------------------------------------------------
Reserve Estimation
The PEA prepared by Golder Associates in July 2009 provided for a probable economic reserve of 309,000 tonnes based on the 2005 InnovExplo resource estimate. The Prefeasibility Study provides for 689,829 tonnes based on the 2009 O'Dowd resource estimate and a gold price related reduction in the cut-off grade.
This Study also provides a complete update on the information provided in the PEA and includes a detailed mine plan and project pricing and economic forecast updates. Mill throughput increased by 109% compared to the PEA. While the life of mine capital expenditures increased due to the increased mined tonnage, the increased production rate and other changes arising from the full review conducted during the Prefeasibility Study, the pre-tax cash flow rose to $47.4 million, an increase of 150% compared to the PEA.
The underground mine reserves were determined using an undiluted cut-off grade of 5.0 g/t and minimum mining width of 1.8 metres. The estimated proven and probable reserves totaled 185,260 oz after applying a mining recovery of 85% for room-and-pillar mining and 95% for long-hole mining, with a dilution factor of 5% for room-and-pillar stopes and 20% for long-hole stopes.
Following is the Mineral Reserve Summary:
------------------------------------------------------------------------- Mineral Reserve Estimate ------------------------------------------------------------------------- Category Undiluted Cut-off 5 g/t Au --------------------------------- tonnes g/tonne ounces ------------------------------------------------------------------------- Proven 13,619 8.00 3,504 ------------------------------------------------------------------------- Probable 676,210 8.37 181,756 ------------------------------------------------------------------------- ------------------------------------------------------------------------- Total Reserve 689,829 8.35 185,260 -------------------------------------------------------------------------
Improvements to the Golder Study
The primary reasons for the improvement over the Golder Study are:
- Resource increase in accordance with the O'Dowd report; - Mine tonnage increase from 309,805 tonnes (82,877 ounces Au) to 689,829 tonnes (185,260 ounces Au); - Mill throughput increase from 400 tpd to 500 tpd; - Improved gold prices; - Recovered gold production increased from 80,806 ounces to 170,556 ounces; - Detailed mine plan completed to facilitate determination of proven and probable reserves; - Major contractors (including potential custom milling partners) and suppliers contacted for updated project pricing; - Implementation of cost reduction measure such as extension of the power line to service the site eliminating the use of high cost generators.
Mining
The underground mine design provides for a mine plan containing 689,829 tonnes of ore assaying 8.35 g/tonne. Total mine ore production over the current five-year mine plan is expected to be 180,629 oz.
A summary of the annual mine plan is as follows:
------------------------------------------------------------------------- Year Gold Ore Mined Ore Milled Production (tonnes) (tonnes) (oz) ------------------------------------------------------------------------- Pre-production ------------------------------------------------------------------------- 14 months 44,596 42,000 10,073 ------------------------------------------------------------------------- 1 172,500 172,500 45,631 ------------------------------------------------------------------------- 2 172,500 172,500 45,249 ------------------------------------------------------------------------- 3 172,500 172,500 40,495 ------------------------------------------------------------------------- 4 127,733 130,329 39,181 -------------------------------------------------------------------------
The mining method will be 80/20 ratio of room-and-pillar mining and long hole mining. For stopes less than 45 degrees the mining method will be room and pillar with long hole for the remaining stopes. Contractors will be utilized for all mine development, mine production and ore haulage activities. A small staff workforce will be hired to provide technical support and direction to the contractors.
Processing and Metallurgy
Ore from Croinor will be processed at a mill in the Val-d'Or area which will have excess capacity for the duration of the Croinor operation. Contact has been made with potential custom milling partners and tentative commitments have been arranged for processing the ore. Ore previously mined from the Croinor open pit operations was processed at a mill in the area and based on actual results achieved during these runs, a gold recovery of 97.5% has been used in this Study. 42,000 tonnes of ore which will be processed during the pre-production period is deemed to be capital production and is not included in production nor is the revenue derived there from. Life of mine gold production is 170,556 ounces.
Infrastructure
A 25 KV transmission line will be extended from the nearby Chimo mine site to the Croinor site to supply electrical power for the site.
The existing roads to and on the site will be upgraded to support vehicle travel to and from the site including the offsite transportation of ore for processing.
The mine will be dewatered and the existing 300-meter ramp and 2 km mine level development will be reconditioned and extended to meet mine requirements. The existing 200-meter deep shaft will be reconditioned and used as a ventilation raise and emergency escape way. Ore and waste haulage to surface will be via ramp.
One existing building will be set up for use as a garage and additional buildings will be constructed to serve as dry, offices and core shack.
Operating Costs
Operating costs over the life of mine are projected to average US$572 per oz. The cost distribution is as follows:
------------------------------------------------------------------------- $/tonne milled US$/oz Au produced ------------------------------------------------------------------------- Mining ------------------------------------------------------------------------- Direct 61.69 219 ------------------------------------------------------------------------- Indirect 34.28 122 ------------------------------------------------------------------------- Milling & ore transportation 43.00 154 ------------------------------------------------------------------------- Surface services 0.59 2 ------------------------------------------------------------------------- Administration 11.96 44 ------------------------------------------------------------------------- Energy Cost 7.57 27 ------------------------------------------------------------------------- Environment 1.20 4 ------------------------------------------------------------------------- Total operating cost (LOM) 160.30 572 -------------------------------------------------------------------------
Capital Costs
The capital cost estimate is accurate within +/- 20%.
The pre-production costs are estimated at $18.59 million including capitalized operating costs, net of production revenue of $2.17 million received during the pre-production period. Sustaining capital is estimated at $7.4 million excluding $0.62 million for final closure costs.
The cost breakdown is as follows:
------------------------------------------------------------------------- $M ------------------------------------------------------------------------- Pre-Production Sustaining Total ------------------------------------------------------------------------- Description ------------------------------------------------------------------------- Capitalized operating cost 14,46 0 14.46 ------------------------------------------------------------------------- Capitalized revenue from production- -12.29 0 -12.29 ------------------------------------------------------------------------- Dewatering and mine rehabilitation 1.44 0 1.44 ------------------------------------------------------------------------- Mine development 6.67 6.75 13.42 ------------------------------------------------------------------------- Ventilation 0.25 0 0.25 ------------------------------------------------------------------------- Mine dewatering 0.42 0 0.42 ------------------------------------------------------------------------- Surface infrastructure 1.40 0 1.40 ------------------------------------------------------------------------- Electrical infrastructure 4.98 0.38 0.38 ------------------------------------------------------------------------- Buildings 0.84 0 0.84 ------------------------------------------------------------------------- Environment 0.42 0.23 0.65 ------------------------------------------------------------------------- Demobilization 0 0.02 0.20 ------------------------------------------------------------------------- Total Capital 18.59 7.38 25.98 ------------------------------------------------------------------------- ------------------------------------------------------------------------- Closure 0.62 0.62 -------------------------------------------------------------------------
Financial Details
The financial analysis for the base case (Bloomberg consensus gold and exchange rate forecast) provides for a pre-tax undiscounted NPV of $47.4 M with an IRR of 97%. Discounted at 7%, the NPV is $35.9M. Using the 3-year trailing average, the project undiscounted NPV is $24.9M and the IRR is 52%.
Sensitivity analysis
Sensitivity of the Croinor project to certain operating and financial factors has been analyzed in order to determine the robustness of the investment to the variation of these factors to those estimated.
The sensitivity has been carried out on the economic model of the project and is represented as changes to the undiscounted Net Present Value (NPV) from the Bloomberg base case. The factors considered to have the greatest impact are the ore grade, gold price, operating cost and capital cost. The following table demonstrates the impact of 10 % and 20% changes in these parameters on the project undiscounted NPV
Sensitivity Analysis. Undiscounted NPV ( $M) ------------------------------------------------------------------------- Parameter Change ------------------------------------------------- -20% -10% Base Case 10% 20% ------------------------------------------------------------------------- Ore grade 37.8 42.6 47.4 52.1 56.9 ------------------------------------------------------------------------- Gold price 14.2 30.8 47.4 64 80.5 ------------------------------------------------------------------------- Operating cost 64.9 56.1 47.4 38.6 29.9 ------------------------------------------------------------------------- Capital Cost 51.7 49.6 47.4 45.2 43 -------------------------------------------------------------------------
OUTLOOK
Subject to successful project financing, mine dewatering is expected to commence during the fourth quarter of 2010. Commercial production is anticipated 14 months following commencement of dewatering. During the pre-production period, 42,000 tonnes of ore will be processed and 10,073 oz of gold will be produced commencing in the 10th month following the announcement of the decision to commence mine dewatering.
The project exhibits significant opportunities to improve on the project economics:
- Completion of infill and down plunge exploration drilling aimed at expanding the current resources and reserves. A 6,050-meter program is ongoing and will be completed during the fourth quarter of 2010; - Reinterpretation of the vein structure with further drilling could increase the ratio of lower cost long-hole stoping to room-and-pillar mining; - Mining of a small open-pitable resource located west of the existing west pit and recovery of remnant ore in the existing west pit; - Incorporation of technology such as gravity separation to reduce mill operating cost. - Evaluation of the potential to apply ore sorting technology at the Croinor site.
Blue Note, as operator of the joint venture, is proceeding with other engineering studies and reports required for the development of the project. Blue Note expects to have everything in place to begin mine dewatering by the fourth quarter of 2010, subject to the receipt of the government approval to operate which is now expected to be received by the end of August.
Qualified Persons
The technical and scientific content of this press release has been reviewed by Sylvie Poirier , P. Eng, Independent QP, InnovExplo Inc.; John Martin, P. Eng., President and Chief Operating Officer of Blue Note Mining Inc.; Qualified Persons as defined under Regulation 43-101 guidelines.
About Blue Note Mining
Blue Note Mining is a mineral exploration and mining company headquartered in Montreal with properties located in known gold regions of Canada, including the prolific Val-d'Or region of Quebec and northern New Brunswick. Blue Note's top priority is to put the Croinor Gold Property into production.
About First Gold Exploration
The goal of the Company is to create shareholder value by acquiring promising projects that could be advanced to production stage in a short period of time. It has now done so, with its 50% owned Croinor project, doing the same format with its Rare Metal property Pivert/Rose and working the others that got chosen for their promising features (San Javier silver property and Matchi-Manitou project).
Forward-Looking Statements
This news release contains discussion of items that may constitute forward-looking statements within the meaning of securities laws that involve risks and uncertainties. Although the company believes the expectations reflected in such forward-looking statements are based on reasonable assumptions, it can give no assurances that its expectations will be achieved. Factors that could cause actual results to differ materially from expectations include the effects of general economic conditions, actions by government authorities, uncertainties associated with contract negotiations, additional financing requirements, market acceptance of the Company's products, technical uncertainties associated with operating an underground mine and competitive pressures. These factors and others are more fully discussed in Company filings with Canadian securities regulatory authorities.
"Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release."
For further information: Blue Note shareholders: Jean Mayer, Executive Vice President, (800) 937-3095 x 236, [email protected]; www.bluenotemining.ca; First Gold shareholders: Eric Leboeuf, President and Chief Executive Officer, (514) 862-6889, [email protected]; www.firstgoldexploration.com
Share this article