CGA ANNOUNCES A NEW DAILY THROUGHPUT PRODUCTION RECORD
/NOT FOR DISSEMINATION IN THE UNITED STATES OR FOR RELEASE TO US NEWS WIRE SERVICES/
ANNOUNCEMENT TO THE AUSTRALIAN SECURITIES EXCHANGE AND TORONTO STOCK EXCHANGE
PERTH, Western Australia, Nov. 12 /CNW/ - The Board of Directors of CGA Mining Limited (CGA:TSX and CGX:ASX) is pleased to announce the achievement of a new daily throughput production record at the Masbate Gold Project.
Over the 24 hour period of 10 November 2010, 21 831 dry tonnes were processed at a throughput rate of 926dtph. The previous record was 20 526t which was announced 10 May 2010.
The plant at the Masbate Gold Project continues to perform well and exceed all expectations.
In the September Quarter the Masbate Gold Project produced 48 373 ounces at cash operating costs of $587/ounce. Throughput was 1 447 557t for a grade of 1.27g/t and a recovery of 85.9%. Availability was up to 91% (June Quarter 87.4%).
ABOUT CGA MINING LIMITED
CGA is listed on both the Toronto Stock Exchange and the Australian Securities Exchange. The Masbate Gold Project is the largest gold project in the Philippines and was successfully developed with first gold poured on 12 May 2009. The project has a total indicated resource base of 4.55M ounces, total inferred resource base of 3.22M ounces and a probable reserve of 3.03M ounces of gold. At steady state operations the project is forecast to produce over 200,000 ounces per annum.
The 4Mtpa designed plant was constructed by Leighton Contractors Asia Limited ("Leighton") without one lost time injury. The mining contract for the Masbate Gold Project has been awarded to Leighton, the largest mining contractor in the world. The plant is currently running at an annualised rate in excess of 6Mtpa. CGA is completing a US$15M investment program designed to upsize throughput to 6.5Mtpa at Masbate.
CGA has a disciplined acquisition program focused on acquiring new gold projects with a substantial initial resource with the capacity to grow materially and where the development and operational experience of CGA can be applied to enhance shareholder value.
NATIONAL INSTRUMENT 43-101 AND JORC COMPLIANCE
Mr Geoff.G.Jones, F.Aus.I.M.M.CP Mng, CGA's Consulting Engineer, is acting as the Qualified Person in compliance with NI 43-101 and JORC reporting requirements with respect to this announcement. He has prepared and or supervised the preparation of the scientific or technical information in this announcement and confirms compliance with NI43-101 and JORC requirements.
Further information relating to the Masbate Project is included in the technical report entitled Technical Report on the Mineral Resources of the Masbate Deposit, Masbate Province, Republic of the Philippines for CGA Mining Limited prepared by Mining Associates Pty Ltd and available on SEDAR at sedar.com, lodged 8 July 2008.
Andrew James Vigar of Mining Associates Pty Ltd, a qualified person, has verified the resource statement for the Masbate Project as disclosed in this announcement, including sampling, analytical and test data underlying the estimate. Verification of the data included numerous site visits, database validation of historical drill results and review of sampling and assaying protocols. The qualified person was satisfied with the verification process.
A NI 43-101 compliant report has been lodged on sedar.com verifying and supporting the new reserve statement made for the Masbate Project. Mr Daniel Tuffin, previously of Lower Quartile Solution Pty Ltd, a qualified person, has verified the reserve statement for the Masbate Project as disclosed in this announcement, including sampling, analytical and test data underlying the estimate. Verification of the data included database validation of historical drill results and review of sampling and assaying protocols. The qualified person was satisfied with the verification process.
CAUTIONARY NOTE REGARDING FORWARD LOOKING STATEMENTS
This announcement includes certain "forward-looking statements" within the meaning of Canadian securities legislation. All statements, other than statements of historical fact, included herein including, without limitation, milestones related to the Masbate Gold Project, production estimates and CGA's future operating or financial performance, are forward-looking statements. Forward-looking statements involve various risks and uncertainties and are based on certain factors and assumptions. There can be no assurance that such statements will prove to be accurate, and actual results and future events could differ materially from those anticipated in such statements. Important factors that could cause actual results to differ materially from CGA's expectations include uncertainties related to fluctuations in gold and other commodity prices and currency exchange rates; uncertainties relating to interpretation of drill results and the geology, continuity and grade of mineral deposits; uncertainty of estimates of capital and operating costs, recovery rates, production estimates and estimated economic return; the need for cooperation of government agencies in the development of CGA's mineral projects; the need to obtain additional financing to develop CGA's mineral projects.; the possibility of delay in development programs or in construction projects and uncertainty of meeting anticipated program milestones for CGA's mineral projects; and other risks and uncertainties disclosed under the heading "Risk Factors" in CGA's Annual Information Form for the year ended 30 June 2010 filed with the Canadian securities regulatory authorities on the SEDAR website at sedar.com
For further information:
ENQUIRIES
Australian Contact President & CEO - Michael Carrick |
US Contact Independent Chairman - Mark Savage |
Tel: +61 8 9263 4000 Fax: +61 8 9263 4020 Email: [email protected] |
Tel: +1 505 344 2822 Fax: +1 505 344 2922 Email: marksavage@comcast.net |
Share this article