PERTH, Australia, April 30, 2012 /CNW/ - Elemental Minerals Ltd. (ASX, TSX: ELM) ("Elemental" or "the Company") is pleased to provide the following quarterly update.
ACTIVITIES
Pre-Feasibility Study and Phase 2 Exploration Programme
The Company continued with the pre-feasibility phase of its definitive feasibility study ("DFS") for the Sintoukola potash project this quarter. The Phase 2 resource drilling was completed. 12 boreholes (3,914 metres) were drilled to bring the final total to for Phase 1 and Phase 2 resource holes to 36 (11,954 metres). Some of these boreholes also served to provide geotechnical samples and data for the PFS.
An additional 4 boreholes (930 metres) were drilled for hydro-geological purposes during the quarter to provide data for the Company's PFS. A further 3 holes are in progress and planned to complete this phase of hydrological study.
Resource boreholes completed during the Quarter with intersections reported are given in Table 1.
Sampling and Analyses
Drill core samples (PQ core diameter sizes) are split in half by a diamond saw cutting machine at the project site. The half split samples, each weighing about three to seven kilograms, are collected at an average interval of 0.3 to 1.0 metre. The samples were processed and analysed by Genalysis, Perth, Australia. Sample preparation and analysis is done by Genalysis. Potassium, Sodium, Calcium, Magnesium, Chlorine, and Sulphur were analysed by ICP-ES. Routine international-standard QA/QC procedures were used by Genalysis. One of the six elements analysed are reported here: potassium (K) and its molecular equivalent of Potassium oxide (K2O, by multiplication with a factor of 1.204). The detection limit for K is 0.001%.
Hole | Zone | From (m) |
To (m) | True Width (m) |
% K2O | % KCl |
EK_17 | Upper Seam | 256.25 | 260.43 | 4.18 | 22.63 | 35.85 |
EK_17 | Lower Seam | 263.33 | 268.47 | 5.14 | 19.78 | 31.32 |
EK_18 | Upper Upper Seam | 286.59 | 290.45 | 3.86 | 16.14 | 25.57 |
EK_18 | Lower Upper Seam | 290.7 | 300.26 | 9.56 | 20.69 | 32.78 |
EK_19 | Upper Seam | 278.22 | 282.76 | 4.54 | 21.58 | 34.18 |
EK_19 | Lower Seam | 285.9 | 288.29 | 2.39 | 20.95 | 33.19 |
EK_20 | Upper Seam | 245.85 | 249.96 | 4.11 | 23.89 | 39.16 |
EK_20 | Lower Seam | 252.76 | 261.76 | 9 | 11.55 | 18.94 |
EK_23 | Upper Seam | 296.32 | 300.36 | 4.04 | 23.49 | 37.29 |
EK_23 | Lower Seam | 303.56 | 312.53 | 8.97 | 11.08 | 17.58 |
EK_26 | Upper Seam | 311.25 | 317.83 | 6.58 | 16.38 | 25.94 |
EK_26 | Lower Seam | 320.9 | 327.38 | 6.48 | 12.55 | 19.88 |
EK_27 | Upper Seam | 306.92 | 310.22 | 3.3 | 27.41 | 43.41 |
EK_27 | Lower Seam | 313.15 | 318.09 | 4.94 | 19.27 | 30.52 |
EK_29 | Upper Seam | 291.87 | 299.69 | 7.82 | 14.33 | 22.69 |
EK_29 | Lower Seam | 303.2 | 313.05 | 9.85 | 11.05 | 17.5 |
EK_31 | Upper Seam | 274.59 | 281.14 | 6.56 | 12.21 | 20.01 |
EK_31 | Lower Seam | 284 | 292.61 | 8.61 | 10.48 | 17.17 |
Table 1. Drill hole intersections reported during the Quarter. In EK_21 and EK_30 the borehole failed above the expected seam intersection. Complete sample submission for EK_22, EK_24, EK_28 pending. In EK_25 no seam was intersected.
Hole | East- WGS84 |
West-WGS84 | RL | Depth | Azimuth | Dip | Assays |
EK_17 | 797507 | 9546422 | 46.449 | 337.6 | 0 | -90 | Reported |
EK_18 | 794975 | 9547597 | 25 | 317.45 | 0 | -90 | Reported |
EK_19 | 798398 | 9548053 | 38.12 | 302.06 | 0 | -90 | Reported |
EK_20 | 795332 | 9548799 | 25 | 320.45 | 0 | -90 | Reported |
EK_21 | 795922 | 9547947 | 25 | 209.88 | 0 | -90 | |
EK_22 | 800877 | 9541993 | 31.92 | 378.16 | 0 | -90 | |
EK_23 | 801321 | 9542833 | 25 | 362.45 | 0 | -90 | Reported |
EK_24 | 799460 | 9542813 | 39 | 345.22 | 0 | -90 | |
EK_25 | 797872 | 9541357 | 25 | 287.3 | 0 | -90 | |
EK_26 | 796930 | 9542690 | 25 | 383.25 | 0 | -90 | Reported |
EK_27 | 803063 | 9542100 | 25 | 365.35 | 0 | -90 | Reported |
EK_28 | 798006 | 9544396 | 25 | 339.22 | 0 | -90 | |
EK_29 | 801309 | 9541101 | 27.437 | 368.4 | 0 | -90 | Reported |
EK_30 | 801888 | 9542032 | 14.91 | 237.6 | 0 | -90 | |
EK_31 | 797969 | 9548724 | 35.172 | 344.25 | 0 | -90 | Reported |
EK_32 | 795476 | 9550548 | 18.199 | 302.3 | 0 | -90 | |
EK_33 | 794738 | 9548513 | 15.31 | 332.3 | 0 | -90 | |
EK_34 | 799125 | 9547432 | 53.08 | 264.15 | 0 | -90 | |
EK_35 | 795573 | 9546516 | 22.81 | 278.3 | 0 | -90 | |
EK_36 | 796809 | 9544911 | 33.56 | 353.3 | 0 | -90 |
Table 2. Drillholes completed during the Quarter. In EK_21 and EK_30 the borehole failed above the expected seam intersection. Complete sample submission for EK_22, EK_24, EK_28 and EK_32 to EK_36 pending. In EK_25 no seam was intersected.
Pre-Feasibility Trade-Off Studies
The study team consisting of Elemental staff, SRK Consulting, AMEC Americas and EGIS International advanced the Pre-Feasibility study, with good progress having been achieved in the following areas.
Geotechnical study: The field geotechnical drilling and logging was completed. Laboratory testing and engineering characterization was completed. 2D finite element analysis is in progress to determine mine design criteria.
Hydrogeological study: Piezometer testing on 10 hydrogeological holes was completed by SRK (US) during January and February 2012. The drilling and equipping of two well sets each comprising 4 holes was partially completed during February and March. Preliminary evaluation of the results obtained from well site A started, using numerical ground water modeling. Five day pump test was started on well site B and a short term airlift tests was completed on this site. Further slug testing and completion of additional wells at each well site will continue into the 2nd Quarter.
Mining: Preparation work for the PFS mining study continued in anticipation of issuing the resource upgrade in Q2, 2012. Further definition of the shaft design, ventilation design, panel design and equipment selection was achieved. The impact of exclusion zones was assessed on a preliminary basis. The mining cost estimate was advanced.
Processing: Amec has revised the mass balance, process flow diagrams, 3D modeling and general layouts based on a decision to reduce the feed grade to 23.3%K2O as a consequence of mining the full upper seam. Process flow diagrams were adjusted to allow for a twin stream design. A trade off study was completed on the final plant position, considering the coastal topography and it was recommended to have the complete plant and offloading facilities on the coastal plane. This allowed the site layout to be finalized. Another trade off study was completed on various ROM storage options.
Preparation was done for the final estimating and an additional test program was initiated to conduct mineralogical characterization and liberation analysis on the US2 material.
Tailings storage facility: SRK (Perth) completed site selection of the TSF and commenced with design of the TSF site.
Infrastructure: Study work continued on the following disciplines:
Basic designs were completed and estimation is underway.
Environmental and Social Impact Assessment: The following activities have been completed as part of the environmental and social impact assessment studies, which are managed by SRK Consulting:
Project Management: In preparation of the estimating phase, work has proceeded on final definition of the Work Breakdown Structure, estimating methodology and economic modelling requirements.
About Elemental Minerals
Elemental Minerals Limited is an advanced mining exploration and development company that aims to grow shareholder value through its 93%-owned Sintoukola Potash Project on the Republic of Congo coastline. Elemental Minerals is dual listed on the Australian Stock Exchange and the Toronto Stock Exchange under the symbol ELM. For more information, visit www.elementalminerals.com
Mineral Resource Summary - Kola Deposit of Sintoukola Project
Competent Person / Qualified Person Statement:
Information in this report that relates to Exploration Results or Mineral Resources is based on information compiled by Simon Dorling and Jeff Elliott, of CSA Global Pty Ltd, the Company's geological consultants. Dr. Dorling and Mr. Elliott are members of the Australian Institute of Geoscientists (MAIG) and have sufficient experience relevant to the style of mineralisation and type of deposit under consideration and to the activity they are undertaking to qualify as a Competent Person as defined in the 2004 Edition of the "Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves" (the JORC Code). Dr. Dorling and Mr. Elliott are also Qualified Persons for the purposes of Canadian National Instrument 43-101 and they consent to the inclusion in this report of the Information, in the form and context in which it appears.
Forward-Looking Statements:
This review of operations contains statements that are "forward-looking". Generally, the words "expect," "potential", "intend," "estimate," "will" and similar expressions identify forward-looking statements. By their very nature, forward-looking statements are subject to known and unknown risks and uncertainties that may cause our actual results, performance or achievements, to differ materially from those expressed or implied in any of our forward-looking statements, which are not guarantees of future performance. Statements in this review of operations regarding the company's business or proposed business, which are not historical facts, are "forward looking" statements that involve risks and uncertainties, such as resource estimates and statements that describe the company's future plans, objectives or goals, including words to the effect that the company or management expects a stated condition or result to occur. Since forward-looking statements address future events and conditions, by their very nature, they involve inherent risks and uncertainties. Actual results in each case could differ materially from those currently anticipated in such statements.
Investors are cautioned not to place undue reliance on forward-looking statements, which speak only as of the date they are made.
Image with caption: "Figure 1: Location of Sintoukola Potash License (CNW Group/Elemental Minerals Limited)". Image available at: http://photos.newswire.ca/images/download/20120430_C2260_PHOTO_EN_12855.jpg
Image with caption: "Figure 2: Kola Phase 2 Drill Map showing progress to end Quarter 1, 2012. (CNW Group/Elemental Minerals Limited)". Image available at: http://photos.newswire.ca/images/download/20120430_C2260_PHOTO_EN_12856.jpg
Contacts:
Iain Macpherson
Chief Executive Officer
Tel: +27 (0) 76 238 4461
[email protected]
John Sanders
Executive Director
Tel: +27 (0) 82 445 5291
john.sanders@elementalmineralsltd.com
Ilja Graulich
Investor Relations Manager
Tel: +27 (0) 83 604 0820
[email protected]
Johannesburg Office: +27 11 469 9140
Share this article