The Company has completed its first two test wells on the Oscar C lease in Medina County, Texas. Both wells are producing oil from the Olmos formation. The Company recently received two additional drilling permits on the Oscar C lease to drill to the base of the Olmos formation. The Escondido zone which overlies the Olmos will also be tested. The Company and its partners plan a ten-well program immediately following the four exploratory test wells.
CENTRAL ALBERTA ---------------
Pipeline construction operations are completed at Chigwell 5-31-42-25 W4. The pipeline was bored under Highway 2A and the Ponoka Airport and tied into above-ground facilities at 6-36-42-25 W4. Facilities are being completed with initial production expected to begin within the next 7-10 days.
At Gilby, Alberta, the Company is awaiting final approval of the facilities drawings prior to the filing of the pipeline license application. Approval of the drawings is expected within the next 10 days. Tie-in construction is scheduled to begin the week of
At Joffre, Alberta, Independent Operations Notices for the pipeline facilities have been sent to partners and operations to tie in the first of two recently drilled CBM wells is expected to commence the week of
At Lacombe, Alberta, the Company will tie-in three wells prior to year-end. Surveys and land agreements are being completed and construction is anticipated to begin in late November or early December.
At Alliance, Alberta, swab testing operations produced oil from the Viking perforations. The Company is currently planning for its production facilities and a possible stimulation on the Viking interval.
ABOUT EMERALD BAY
If you would like to receive press releases via email please contact [email protected]. Please specify "
Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release. ------------------------------------------------------------------------- Forward-Looking Statements --------------------------
This press release includes statements that may constitute "forward-looking" statements, usually containing the words "believe," "estimate," "project," "expect", "plan", "intend", "anticipates", "projects", "potential" or similar expressions.. Forward-looking statements inherently involve risks and uncertainties that could cause actual results to differ materially from the forward-looking statements. Forward-looking statements are statements that are not historical facts.
Information inferred from the interpretation of drilling results may also be deemed to be forward looking statements, as it constitutes a prediction of what might be found to be present when and if a well is actually developed. BOE's may be misleading, particularly if used in isolation. A BOE conversion ratio of 6 Mcf: 1 Bbl is based on energy equivalency conversion method primarily applicable at the burner tip and does not represent a value equivalency at the wellhead. The reader is cautioned that assumptions used in the preparation of such information, which are considered reasonable by
%SEDAR: 00008937E
For further information: Emerald Bay President, Shelby D. Beattie, by telephone at (403) 262-6000 or by email at [email protected]; or CHF Investor Relations: Catarina Cerqueira, Associate Account Manager, (416) 868-1079 x251, [email protected]; Robin Cook, Senior Account Manager, (416) 868-1079 x228, [email protected]
Share this article