LONGUEUIL, QC, April 26 /CNW Telbec/ - The Jacques Cartier and Champlain Bridges Incorporated (JCCBI) wishes to announce the start of construction on Viaduct 3 which will cause the night-time closure of Exit 57 N from Highway 15 South as well as of l'île-des-Sœurs Boulevard North and South located under the Bonaventure on ramp (Viaduct AB).
These closures will occur on the night of Thursday, April 29 to Friday, April 30 from 10:00 PM to 5:00 AM. Please note that l'île-des-Sœurs Boulevard toward Pointe Nord will also be closed from 9:00 PM from the traffic circle at the intersection of Place du commerce and l'île-des-Sœurs Boulevard.
These closures will allow formwork for the new Viaduct 3 to be completed. Detours will be indicated to facilitate traffic in the area. Users coming from Highway 15 South should use Exit 57 to access Pointe Nord on L'Île-des-Sœurs. In the opposite direction, a detour via Brossard and Highway 15 North will be indicated to access Pointe Nord on the island.
Partial daytime blocking of l'île-des-Sœurs Boulevard is anticipated over the subsequent weeks in order to complete the form and cement work begun at night.
Follow this project on Twitter: http://twitter.com/PontChampBridge
Consult our map that presents the closures: http://bit.ly/9Igyax
For further information: Jean-Vincent Lacroix, Chef, Communications, Jacques Cartier and Champlain Bridges Incorporated (JCCB), Office: (450) 651-8771, ext. 232, Cell: (514) 249-1940, [email protected]; Émilie Thibault, AGC Communications, Office: (514) 849-7000, ext. 231, Cell: (514) 825-7365, [email protected]; Source: André Girard, Vice President, Communications, Jacques Cartier and Champlain Bridges Incorporated, (450) 468-5775, [email protected]