(In United States dollars, except where noted otherwise)
TORONTO, Feb. 14, 2019 /CNW/ - First Quantum Minerals Ltd. ("First Quantum" or the "Company", TSX Symbol "FM") today reported comparative earnings1 of $182 million ($0.26 per share1), net earnings attributable to shareholders of the Company1 of $198 million ($0.29 per share) and cash flows from operating activities of $338 million ($0.49 per share1) for the three months ended December 31, 2018 ("Q4").
For the full year 2018, the Company reports comparative earnings1 of $487 million ($0.71 per share1), net earnings attributable to shareholders of the Company1 of $441 million ($0.64 per share1) and cash flows from operating activities of $1,980 million ($2.88 per share1).
FOURTH QUARTER AND FULL YEAR 2018 SUMMARY:
- Operations Delivered Solid Results with Lower Costs
- 158,304 tonnes of copper2 produced in Q4:
- Record Q4 production at Sentinel of 60,840 tonnes, reflecting continued improvement quarter over quarter in production and costs.
- Q4 Unit cost of copper production3: All-in sustaining cost ("AISC") = $1.68 per pound; Cash cost ("C1") = $1.23 per pound; Total cost ("C3") = $2.04 per pound.
- 605,853 tonnes of copper2 produced for the full year.
- 2018 full year unit cost of copper production3: AISC = $1.74 per pound; C1=$1.28 per pound; C3=$2.11 per pound.
- Strong Operating Cash Flows and Continued Liquidity; Dividend Declared
- $338 million of cash flows from operating activities ($0.49 per share3) during the quarter, an increase of 67% from the comparable prior year period.
- $1,980 million of cash flows from operating activities ($2.88 per share1) during all of 2018.
- Ended the quarter and year with $788 million in net unrestricted cash and cash equivalents, $700 million of committed undrawn facilities and in full compliance with all financial covenants.
- Final dividend declared of CDN$0.005 in respect of the 2018 year-end; total dividends for the full year 2018 were CDN$0.01.
- Cobre Panama Project nears completion as of year-end.
- The focus at the Cobre Panama project remains on construction completion, commissioning of the process plant and commissioning and ramp-up of the power station. During the quarter, project pre-strip was completed, engineering and procurement were essentially completed, and the tailings management facility earthworks advanced to 87% completion. Construction of the two power sets was completed in the quarter with commissioning being well advanced with the reliability and ramp-up program for set 1 completed in January 2019. Set 2 is in full commissioning with synchronization to the grid having occurred in January 2019. Extensive process plant commissioning and testing were ongoing throughout the quarter in preparation for production. First ore was introduced to the mill on February 11, 2019. The project remains scheduled for ramp-up over 2019 and 2020.
- During 2019, Cobre Panama mine is expected to produce 140,000 – 175,000 tonnes of contained copper and by year end be running at an annualized rate of 72 million tonnes per year ("mtpa"). Limited copper production is expected in the first half of 2019 while the commissioning and start-up continues with approximately 80% of production expected to occur in the second half of the year. Commercial production will be declared in arrears and is expected to occur in the final quarter of 2019.
- In 2020, contained copper production of between 270,000-300,000 tonnes is expected as a throughput rate of 85 mtpa is reached. In 2021, production of approximately 300,000 tonnes of contained copper is expected, increasing in 2022 to 350,000 tonnes. In 2022, the C1 unit cost of production is estimated at $1.20 per lb and $1.50 per lb all-in sustaining. Both estimates are net of an assumed by-product credit principally gold as well as some molybdenum and silver, of approximately $0.25 per lb. Gold production in 2020 and 2021 is estimated at approximately 100,000 ounces per year.
CEO'S COMMENTS
"2018 was a very important year for the Company with the development of Cobre Panama nearing completion. We achieved record production for the year, ahead of target, and in line with the expected low unit production costs. Much of this was due to a 17% increase in production at Sentinel," noted Philip Pascall, Chairman and CEO. "Our financial results for the quarter and the full year reflect this strong operating performance through the year."
"2019 will be another important year for the Company. With Cobre Panama starting operation, and the continuing steady production from our existing mines, we expect significantly higher output. I appreciate and laud our staff and employees for what was accomplished in 2018 and look forward to another exciting and productive year," Mr. Pascall concluded.
OPERATING HIGHLIGHTS
Three months ended |
Full year ended |
|||
(U.S. dollars where applicable) |
2018 |
2017 |
2018 |
2017 |
COPPER |
||||
- Production2 (tonnes) |
158,304 |
154,319 |
605,853 |
573,963 |
- Sales4 (tonnes) |
156,212 |
151,905 |
596,513 |
580,130 |
- Cost of production3: |
||||
o AISC (per lb) |
$1.68 |
$1.76 |
$1.74 |
$1.65 |
o C1 (per lb) |
$1.23 |
$1.30 |
$1.28 |
$1.23 |
o C3 (per lb) |
$2.04 |
$2.16 |
$2.11 |
$2.05 |
- Realized price (per lb) |
$2.83 |
$2.50 |
$2.84 |
$2.33 |
GOLD |
||||
- Production (ounces) |
48,039 |
51,904 |
185,414 |
199,736 |
- Sales (ounces) |
53,221 |
50,723 |
193,072 |
201,376 |
FINANCIAL HIGHLIGHTS
Three months ended |
Full year ended |
|||
(U.S. dollars millions, except where noted otherwise) |
2018 |
2017 |
2018 |
2017 |
Sales revenues Gross profit
Net earnings (loss) attributable to shareholders of the Company Basic and diluted earnings (loss) per share
Comparative EBITDA1 Comparative earnings (loss)1 Comparative earnings (loss) per share1
Cash flow from operating activities |
1,054 280
198
$0.29
481 182 $0.26
338 |
885 117
(115)
($0.17)
318 (36) ($0.05)
203 |
3,966 978
441
$0.64
1,737 487 $0.71
1,980 |
3,310 335
(316)
($0.46)
1,154 (111) ($0.16)
914 |
1 Net earnings (loss) attributable to shareholders of the Company has been adjusted to exclude items which are not reflective of underlying performance to arrive at comparative earnings (loss). Comparative earnings (loss), comparative earnings (loss) per share, comparative EBITDA and cash flows per share are not measures recognized under IFRS and do not have a standardized meaning prescribed by IFRS. The Company has disclosed these measures to assist with the understanding of results and to provide further financial information about the results to investors. Refer to the "Regulatory Disclosures" section in the MD&A for the year ended December 31, 2018 for further information. |
|
2 Production is presented on a copper contained basis, and is presented prior to processing through the Kansanshi smelter. |
|
3 AISC, C1 and C3 costs per pound are not recognized under IFRS. Refer to the "Regulatory Disclosures" section in the MD&A for the year ended December 31, 2018 for further information. C1, C3 and AISC costs exclude third-party concentrate purchased at Kansanshi. C1, C3 and AISC costs for Q3 2018 have been revised from amounts previously disclosed to exclude the $0.03 per pound impact of third-party concentrate purchased. |
|
4 Copper sales exclude the sale of copper anode produced from third-party concentrate purchased at Kansanshi. Sales of copper anode attributable to third-party concentrate purchases were 5,884 tonnes and 7,349 tonnes for the three months and year ended December 31, 2018, respectively. Q3 2018 copper sales have been adjusted to exclude copper anode sales of 1,465 tonnes attributable to third-party concentrate purchased. |
Other
- On January 23, 2019, the Company announced a land slippage at Cobre Las Cruces, and production at the hydrometallurgical plant was suspended immediately. Prior to the incident, mine personnel identified a risk and immediately implemented safety protocols. Following the incident, the pit was evacuated and no injuries occurred. On February 1, 2019 the production resumed at the processing plant with the processing of lower grade stockpiled ore which is expected to continue for the next several months while the necessary regulatory approvals are obtained to begin the mining of Phase 6, an area unaffected by the incident.
- On February 6, 2019, the Company signed a new $2.7 billion Term Loan and Revolving Credit Facility underwritten by three core relationship banks. This new Facility replaces the existing $1.5 billion Revolving Credit Facility. The new $2.7 billion Facility (with an accordion feature to increase it up to $3.0 billion before the end of 2019) comprises a $1.5 billion Term Loan Facility and a $1.2 billion Revolving Credit Facility (which can be upsized to $1.5 billion if the accordion feature is activated), maturing on December 31, 2022. This financing includes revised financial covenants, extends the debt maturity profile of the business, demonstrates the Company's access to a diverse range of capital markets, and improves the financial flexibility of the Company through the added liquidity. The Facility will be used for the redemption of the $1,121 million senior notes due February 2021 in full, or in part, and for general corporate purposes.
Production and Cost Outlook
(000's) |
2019 |
2020 |
2021 |
Total Copper (tonnes) |
700 – 735 |
840 – 870 |
820 |
Cobre Panama – Copper2 (tonnes) |
140 - 175 |
270 - 300 |
300 |
Copper2 (tonnes) – excluding Cobre Panama |
560 |
570 |
520 |
Gold (ounces) – excluding Cobre Panama |
185 |
180 |
170 |
Zinc (tonnes) |
12 |
2 |
- |
Production guidance for Las Cruces reflects the land slippage in January 2019, with lost production currently estimated at 25,000 tonnes in 2019. Production at Las Cruces for 2020 has also been reduced by a further 25,000 tonnes from amounts previously disclosed as certain high grade ore is no longer planned to be mined as part of the open pit operation. The open pit mining operations are expected to be completed in the second half of 2020.
In terms of quarterly phasing of annual production, it is expected that production at Zambian operations will be at its lowest in the first quarter. The first and second quarters will also be impacted by lower production at Las Cruces following the land slippage.
The wet season in Zambia generally starts in November and continues through April, with the heaviest rainfall normally experienced in the months of December, January, February and March. As a result of the wet season, pit access and the ability to mine ore is lower in the first quarter of the year than other quarters and the cost of mining is higher.
Cash costs and AISC guidance in the tables below does not include any costs in respect of Cobre Panama.
Copper |
2019 |
2020 |
2021 |
C13 (per lb) |
$1.20 - $1.40 |
$1.20 - $1.40 |
$1.20 - $1.40 |
AISC3 (per lb) |
$1.70 - $1.85 |
$1.70 - $1.85 |
$1.70 - $1.85 |
Increase in AISC guidance reflects higher Zambian royalty and gold sales levy rates effective January 1, 2019. This has increased AISC by $0.05 per lb in all three years. It is expected that a Zambian sales tax will be introduced from April 1, 2019, and that this will result in increased C1 and AISC unit costs. However, guidance given excludes the impact of the sales tax as the rate to be introduced has not yet been confirmed by the Government of the Republic of Zambia.
CONFERENCE CALL & WEBCAST
Conference call and webcast details are as follows:
Date: |
February 15, 2019 |
Time: |
9:00 am (EST); 2:00 pm (GMT); 6:00 am (PST) |
Webcast: |
|
Dial in: |
North America: (toll free) (877) 291-4570 |
North America and international: 1 (647) 788-4919 |
|
United Kingdom: (toll free) 0-800-051-7107 |
|
Replay: |
Available from noon (EST) on February 15, 2019 until 11:59 pm (EST) on March 3, 2019. |
North America: (toll free) (800) 585-8367 |
|
North America and international: 1 (416) 621-4642 |
|
Passcode: |
5469795 |
COMPLETE FINANCIAL STATEMENTS AND MANAGEMENT'S DISCUSSION AND ANALYSIS
The complete consolidated financial statements and Management's Discussion and Analysis for the year ended December 31, 2018 are available at www.first-quantum.com and should be read in conjunction with this news release.
On Behalf of the Board of Directors of First Quantum Minerals Ltd.
G. Clive Newall
President
For further information visit our website at www.first-quantum.com.
CAUTIONARY STATEMENT ON FORWARD-LOOKING INFORMATION
Certain statements and information herein, including all statements that are not historical facts, contain forward-looking statements and forward-looking information within the meaning of applicable securities laws. The forward-looking statements include estimates, forecasts and statements as to the Company's expectations of production and sales volumes, and expected timing of completion of project development at Cobre Panama and Enterprise and are subject to the impact of ore grades on future production, the potential of production disruptions (including at Cobre Las Cruces as a result of the land slippage in January 2019), capital expenditure and mine production costs, the outcome of mine permitting, other required permitting, the outcome of legal proceedings which involve the Company, information with respect to the future price of copper, gold, nickel, zinc, pyrite, cobalt, iron and sulphuric acid, estimated mineral reserves and mineral resources, First Quantum's exploration and development program, estimated future expenses, exploration and development capital requirements, the Company's hedging policy, and goals and strategies. Often, but not always, forward-looking statements or information can be identified by the use of words such as "plans", "expects" or "does not expect", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates" or "does not anticipate" or "believes" or variations of such words and phrases or statements that certain actions, events or results "may", "could", "would", "might" or "will" be taken, occur or be achieved.
With respect to forward-looking statements and information contained herein, the Company has made numerous assumptions including among other things, assumptions about continuing production at all operating facilities, the price of copper, gold, nickel, zinc, pyrite, cobalt, iron and sulphuric acid, anticipated costs and expenditures and the ability to achieve the Company's goals. Forward-looking statements and information by their nature are based on assumptions and involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements, or industry results, to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements or information. These factors include, but are not limited to, future production volumes and costs, the temporary or permanent closure of uneconomic operations, costs for inputs such as oil, power and sulphur, political stability in Zambia, Peru, Mauritania, Finland, Spain, Turkey, Panama, Argentina and Australia, adverse weather conditions in Zambia, Finland, Spain, Turkey, Mauritania and Panama, labour disruptions, potential social and environmental challenges, power supply, mechanical failures, water supply, procurement and delivery of parts and supplies to the operations, and the production of off-spec material.
See the Company's Annual Information Form for additional information on risks, uncertainties and other factors relating to the forward-looking statements and information. Although the Company has attempted to identify factors that would cause actual actions, events or results to differ materially from those disclosed in the forward-looking statements or information, there may be other factors that cause actual results, performances, achievements or events not to be anticipated, estimated or intended. Also, many of these factors are beyond First Quantum's control. Accordingly, readers should not place undue reliance on forward-looking statements or information. The Company undertakes no obligation to reissue or update forward-looking statements or information as a result of new information or events after the date hereof except as may be required by law. All forward-looking statements and information made herein are qualified by this cautionary statement.
SOURCE First Quantum Minerals Ltd.
North American contact: Lisa Doddridge, Director, Investor Relations, Tel: (416) 361-3752, Toll Free: 1 (888) 688-6577, E-Mail: [email protected]; United Kingdom contact: Clive Newall, President, Tel: +44 140 327 3484, E-Mail: [email protected]
Share this article