First Uranium Update on Environmental Authorization
Company Commences a Project Restructuring at MWS, Revises Ezulwini Mine Plan and Undertakes Strategic Review
Strategic Review, Project Restructuring and Capital Limitations
The announcement of the withdrawal of the EA has not only delayed construction of the TSF, it has also disrupted certain well-advanced corporate financing opportunities, which, along with the slower than expected production buildup at the Ezulwini Mine, would, if alternative financing is not obtained, severely compromise the Company's financial position. The Company is now reviewing strategic alternatives, and is engaged in discussions with respect to alternative financing opportunities.
Notwithstanding progress at its operations discussed below, the continuing discussions regarding the EA and the continuing financing discussions, the Company has taken action to delay future development expenditures, particularly at its MWS tailings recovery operation as part of a company-wide program to conserve capital.
The construction of the first uranium plant module will be concluded by the end of
Production at MWS will be scaled back from two gold plants to one at the end of
Under the revised construction schedule the MWS No. 5 Dam will provide sufficient tailings deposition capacity for the one gold plant until the end of
In addition, the Ezulwini Mine development plan is ahead of schedule, however, the mine production forecast has been revised in response to slower than expected mine production ramp up to date and the capital constraints.
MWS: Quarterly Tailings Recovery and Production Forecast ------------------------------------------------------------------------- Q1 2010 Q2 2010 Q3 2010 Q3 2010 Q4 2010 Actual Actual Forecast Actual Forecast ------------------------------------------------------------------------- Tonnes of ore reclaimed (000s) 1,835 2,476 3,880 3,528 2,789 ------------------------------------------------------------------------- Average gold head grade (g/t) 0.42 0.39 0.39 0.36 0.34 ------------------------------------------------------------------------- Gold plant recovery (%) 44% 44% 51% 53% 52% ------------------------------------------------------------------------- Gold reclaimed (oz) 11,007 13,422 25,019 21,891 15,844 ------------------------------------------------------------------------- Note: The increase in gold recoveries is possible through the introduction of gold concentrates into the uranium plant where exposure of material to an acidic environment liberates additional gold that would otherwise not be available for cyanidation. -------------------------------------------------------------------------
At MWS, the Q3 2010 gold produced was less than forecast as the grade reconciliation in the Buffelsfontein No. 4 Dam was slightly below expectations and operations were interrupted by heavy rain storms during the quarter.
The annualized production rate presented below assumes a protracted permitting process during which MWS runs at an average reduced throughput of 600,000 tonnes per month until
MWS: Annual Production Forecast ------------------------------------------------------------------------- FY 2011 FY 2012 ------------------------------------------------------------------------- Gold ------------------------------------------------------------------------- Production (oz) 57,000 64,000 ------------------------------------------------------------------------- Estimated cost ($/oz) 459 490 ------------------------------------------------------------------------- Uranium ------------------------------------------------------------------------- Production (lb) 270,000 560,000 ------------------------------------------------------------------------- Estimated cost ($/lb) 43 36 ------------------------------------------------------------------------- Note: 1. Gold "Cash Costs" are costs directly related to the physical activities of producing gold and include mining, processing and other plant costs; third-party refining and smelting costs; marketing expense, on-site general and administrative costs; royalties; on-mine drilling expenditures that are related to production and other direct costs. Sales of by-product metals are deducted from the above in computing cash costs. Cash costs exclude depreciation, depletion and amortization, corporate general and administrative expense, exploration, interest, and pre-feasibility costs and accruals for mine reclamation. Cash costs are calculated and presented using the "Gold Institute Production Cost Standard" applied consistently for all periods presented. The Gold Institute was a non-profit industry association comprised of leading gold producers, refiners, bullion suppliers and manufacturers. This institute has now been incorporated into the National Mining Association. The guidance was first issued in 1996 and revised in November 1999. Total cash costs per ounce is a non-GAAP measurement and investors are cautioned not to place undue reliance on it and are advised to read all GAAP accounting disclosures presented in the Corporation's audited consolidated financial statements for FY 2009 and accompanying footnotes thereto. 2. Uranium "Cash Costs" calculations take into account the incremental ounces of gold recovered when the ore is run through the atmospheric leach tanks of the uranium plant. -------------------------------------------------------------------------
OUTLOOK - EZULWINI MINE
Production build up at the Ezulwini mine is progressing more slowly than originally anticipated due to the challenges of training and building up the efficiency of the mining crews with the result that the mine has yet to generate positive operating cash flow. Based on the performance to date and the Company's current cash position, the Ezulwini mine plan has been revised as reflected below.
Ezulwini Mine: Quarterly Underground Production Forecast ------------------------------------------------------------------------- Q1 2010 Q2 2010 Q3 2010 Q3 2010 Q4 2010 Actual Actual Forecast Actual Forecast ------------------------------------------------------------------------- Upper Elsburg Mining Activity ------------------------------------------------------------------------- Cumulative metres of mining face available 369 605 749 1,672 1,817 ------------------------------------------------------------------------- Blasted face grade - gold (g/t) 4.66 7.79 6.43 7.42 7.33 ------------------------------------------------------------------------- ------------------------------------------------------------------------- Middle Elsburg Mining Activity ------------------------------------------------------------------------- Cumulative metres of mining face available 408 754 1,131 1,024 1,311 ------------------------------------------------------------------------- Blasted face grade - gold (g/t) 2.95 3.13 3.06 3.20 3.28 ------------------------------------------------------------------------- Blasted face grade - uranium (g/t) 480 439 552 557 560 ------------------------------------------------------------------------- ------------------------------------------------------------------------- Facelength ("FL") Buildup ------------------------------------------------------------------------- Gold (kg/m of FL blasted) 15 28 75 81 91 ------------------------------------------------------------------------- Uranium (kg/m of FL blasted) 1,077 1,377 3,328 2,862 3,690 ------------------------------------------------------------------------- ------------------------------------------------------------------------- Mill Production (combined) ------------------------------------------------------------------------- Tonnes of ore milled (000s) 92 95 145 117 137 ------------------------------------------------------------------------- Notes: 1. Face-length buildup is a metric to indicate the content of gold and uranium produced for a horizontal metre of blasted face length. 2. The current mining rate is not expected to immediately fill the uranium and gold plants that have production capacities of 100,000 tonnes per month and 200,000 tonnes per month, respectively. 3. A minimum three-month delay is expected between uranium production and sales, allowing time for calcining, shipment and conversion. 4. The anticipated increase in stope grades has been determined on the basis of current in situ sampling of reef development and sampling of new stopes that are being opened up. 5. The forecast face length represents the amount of face length available for mining, not necessarily what will be mined. ------------------------------------------------------------------------- Ezulwini Mine: Annual Production Forecast: ------------------------------------------------------------------------- FY 2011 FY 2012 FY 2013 ------------------------------------------------------------------------- Gold ------------------------------------------------------------------------- Production (oz) 133,000 194,000 265,000 ------------------------------------------------------------------------- Estimated by-product cash costs ($/oz) 909 672 634 ------------------------------------------------------------------------- Uranium ------------------------------------------------------------------------- Production (lb) 207,000 312,000 390,000 ------------------------------------------------------------------------- Estimated by-product cash costs ($/lb) 46 40 41 ------------------------------------------------------------------------- Notes: 1. "Cash Costs" are costs directly related to the physical activities of producing gold and include mining, processing and other plant costs; third-party refining and smelting costs; marketing expense, on-site general and administrative costs; royalties; on-mine drilling expenditures that are related to production and other direct costs. Sales of by-product metals are deducted from the above in computing cash costs. Cash costs exclude depreciation, depletion and amortization, corporate general and administrative expense, exploration, interest, and pre-feasibility costs and accruals for mine reclamation. Cash costs are calculated and presented using the "Gold Institute Production Cost Standard" applied consistently for all periods presented. The Gold Institute was a non-profit industry association comprised of leading gold producers, refiners, bullion suppliers and manufacturers. This institute has now been incorporated into the National Mining Association. The guidance was first issued in 1996 and revised in November 1999. Total cash costs per ounce is a non-GAAP measurement and investors are cautioned not to place undue reliance on it and are advised to read all GAAP accounting disclosures presented in the Corporation's audited consolidated financial statements for FY 2009 and accompanying footnotes thereto. 2. The face-length buildup is a metric to indicate the content of gold and uranium produced for a horizontal metre of blasted face length. The cash costs are shown on co-product basis, where costs are allocated to each metal on the basis of the revenue contribution from each metal. -------------------------------------------------------------------------
Q3 2010 PRODUCTION UPDATE
During the quarter ended
Quarterly Production Results ------------------------------------------------------------------------- Q3 2009 Q4 2009 Q1 2010 Q2 2010 Q3 2010 ------------------------------------------------------------------------- Ezulwini ------------------------------------------------------------------------- Total tonnes of ore milled 80,079 108,622 92,468 94,599 108,503 ------------------------------------------------------------------------- Gold produced (oz) 6,411 4,267 3,791 7,952 10,054 ------------------------------------------------------------------------- Gold sold (oz) 6,411 4,267 3,379 7,047 8,213 ------------------------------------------------------------------------- Uranium shipped to converter (lb) - - - - 23,760 ------------------------------------------------------------------------- ------------------------------------------------------------------------- MWS ------------------------------------------------------------------------- Tonnes of ore reclaimed (000s) 1,798 1,693 1,835 2,476 3,528 ------------------------------------------------------------------------- Average gold head grade (g/t) 0.42 0.41 0.42 0.39 0.36 ------------------------------------------------------------------------- Gold plant recovery (%) 50% 47% 44% 44% 53% ------------------------------------------------------------------------- Gold reclaimed (oz) 12,235 10,513 11,007 13,422 21,891 ------------------------------------------------------------------------- Gold sold (oz) 12,581 10,417 10,676 11,739 21,091 ------------------------------------------------------------------------- In Q4 2010, MWS expects to: - commence commissioning of one flotation circuit and the uranium plant. The remaining two flotation circuits, the third gold plant and the TSF will be completed upon reinstatement of the EA and the receipt of funding; - terminate the EPCM contract and dismiss all construction personnel from the project; and - focus production on one of the existing gold plants for an estimated quarterly production of 15,844 ounces of gold. In Q4 2010, the Ezulwini Mine expects to: - open up over 400 metres (net of mining activity) for a total of over 3.1 kilometers of available mining face underground at the Ezulwini Mine; and - record our first sale of uranium.
Technical Disclosure
All technical disclosure in this news release relating to MWS has been prepared in accordance with National Instrument 43-101 ("NI 43-101) by
All technical disclosure in this news release relating to the Ezulwini Mine has been prepared in accordance with NI 43-101 by R.
About First Uranium Corporation
First Uranium Corporation (TSX:FIU, JSE:FUM) is focused on its goal of becoming a significant low-cost producer of uranium and gold through the expansion of the underground development to feed the new uranium and gold plants at the Ezulwini Mine and through the expansion of the plant capacity of the Mine Waste Solutions tailings recovery facility, both operations situated in
Cautionary Language Regarding Forward-Looking Information
This news release contains and refers to forward-looking information based on current expectations. All other statements other than statements of historical fact included in this release including, without limitation, statements regarding the timing and receipt of required permits, the timing and availability of financing on acceptable terms, the timing and amount of estimated future production, processing and development plans and future plans and objectives of First Uranium are forward-looking statements (or forward-looking information) that involve various estimates, assumptions, risks and uncertainties. For more details on these estimates, assumptions, risks and uncertainties, see the Company's most recent Annual Information Form on file with the Canadian provincial securities regulatory authorities on SEDAR at www.sedar.com. These forward-looking statements are made as of the date hereof and there can be no assurance that such statements will prove to be accurate, such statements are subject to significant risks and uncertainties, and actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements that are included herein, except in accordance with applicable securities laws.
For further information: Bob Tait, Vice President, Investor Relations at [email protected], (416) 342-5639 (office) or (416) 558-3858 (mobile), 1240-155 University Avenue, Toronto, ON, M5H 3B7
Share this article