Honoré Mercier Bridge: One Lane Closed at Night toward the South Shore
Weekdays from 10 PM to 10 AM
LONGUEUIL, QC, Aug. 3 /CNW Telbec/ - The Jacques Cartier and Champlain Bridges Incorporated (JCCBI) and the Ministère des Transports du Québec (MTQ) wish to inform the public that one lane will be open to traffic at night toward the South Shore (Châteauguay - La Prairie) weekdays from Monday to Thursday.
The closure of one of two lanes will be repeated for two weeks from Tuesday, August 3 to Thursday, August 5 and Monday, August 9 to Thursday, August 12, from 10 PM to 10 AM in each case.
These closures allow the continuation of the reinforcement of the steel structure of the upstream part of the bridge during weekdays.
For more information, or to follow the progress of our work, please visit the project blog at www.mercierbridge.ca.
For further information:
Jean-Vincent Lacroix Chief, Communications The Jacques Cartier and Champlain Bridges Incorporated (JCCBI) Tel.: 450 651-8771 ext. 232 Cellular: 514 249-1940 [email protected] |
Émilie Thibault AGC Communications Tel.: 514 849-7000 ext. 231 Cellular: 514 825-7365 [email protected] |