AECL provides update on NRU activities
CHALK RIVER, ON,
AECL reports that the NRU reactor vessel repair activities are currently focused on preparation work in advance of the next series of weld repairs. To date, 29 per cent of the repair activities are complete.
In order to ensure that no undesirable structural effects occur to the vessel during repairs, AECL and third-party experts continue parallel stress calculations for each of the next series of weld repairs. The stress calculations consider the geometry of the repair sites, the weld procedure, and the number of layers of weld build up to be applied. Based on the results of the analysis of the stress calculations, AECL engineers have approved the next weld repair.
Two horizontal weld machines are now qualified to proceed with weld repairs. A third horizontal weld machine is undergoing qualification. The AECL and Liburdi Automation Inc. welding teams have completed their reliability practice welds and are qualified to proceed with the next series of repairs.
Plans are being modified to optimize the schedule recognizing that safety and a high quality repair must be maintained. The current schedule targets return to service by the end of
Further guidance on a return-to-service date will be provided when repairs to all sites have been undertaken. The repairs are scheduled to be completed in February.
The first medical isotopes will begin to be removed from the NRU for processing and distribution within 10 days of the reactor being returned to service.
In
The CNSC safety inspectors continue to provide independent regulatory oversight of AECL activities at the Chalk River site.
There is no threat to workers, the public, the environment or nuclear safety related to this event.
For further information: Dale Coffin, Director, Corporate Communications, AECL, 1-866-886-2325
Share this article