Ontario Power Generation reports 2009 third quarter financial results
Net income for the third quarter of 2009 was favourably affected by an increase in earnings from the segregated investment funds that have been established for nuclear fixed asset removal and nuclear waste management (the "Nuclear Funds"). Compared to the same period in 2008, earnings from operations continued to be negatively impacted by a decrease in gross margin related to lower fossil-fuelled generation, lower spot market prices and higher fuel related charges.
"Operational results were significantly affected by a reduction in electricity demand in Ontario and lower spot market prices, which substantially reduced revenue. We continue to focus on enhancing our performance as a public power company committed to operating prudently and efficiently, and on identifying cost reduction opportunities", said President and CEO
Total electricity generated in the third quarter of 2009 of 22.6 terawatt hours ("TWh") was 17 percent lower than third quarter 2008 production of 27.3 TWh. The decrease was mainly as a result of lower generation at OPG's fossil-fuelled stations due to lower primary demand and an increase in generation from other Ontario generators. Unregulated hydroelectric generation declined 0.7 TWh in the third quarter of 2009 compared to the same quarter in 2008 primarily due to lower water levels and the impact of controlled water spills due to unusual Surplus Baseload Generation conditions. Nuclear production increased 0.7 TWh as a result of a decrease in unplanned outage days at the Pickering B nuclear generating station.
For the nine months ended
Capability factors at the Pickering A and B nuclear stations continued to improve during the third quarter of 2009 compared to the same period in 2008, with the Pickering B station achieving a capability factor of 94.2 percent. The Darlington nuclear station reported a capability factor of 91.8 percent in comparison to 99.1 percent in the third quarter of 2008. Hydroelectric availability remained at a high level of 93.2 percent for OPG's regulated stations, and 87.2 percent for the unregulated stations. Improved reliability of the fossil-fuelled stations reflects the change in operating strategy to optimize the number of coal-fired units offered into the electricity market.
Segmented Financial Results
OPG's third quarter income before interest and income taxes was
Third quarter income before interest and income taxes from OPG's electricity generation business segments was
Income before interest and income taxes from OPG's Regulated - Nuclear Waste Management segment was
OPG's income before interest and income taxes was
Income before interest and income taxes from OPG's electricity generation segments was
Income before interest and income taxes from OPG's Regulated - Nuclear Waste Management segment was
Generation Development
OPG is undertaking a number of generation development projects aimed at significantly contributing to Ontario's long-term electricity supply requirements. The status of these projects is as follows:
Nuclear
- On June 29, 2009, the Government of Ontario suspended the competitive
Request for Proposal ("RFP") process to procure two new nuclear
reactors planned for the Darlington site. OPG continued with two
initiatives that were underway - the environmental assessment process
and obtaining a site preparation licence. On September 30, 2009, OPG
submitted the Environmental Impact Statement and an updated
application for the "Licence to Prepare Site" to the Canadian
Environmental Assessment Agency and the Canadian Nuclear Safety
Commission ("CNSC"). On November 16, 2009, the Joint Review Panel
announced the start of the six month public review period for the EIS
and the "Licence to Prepare Site".
- Planning work for the assessment of the feasibility of refurbishing
the Darlington nuclear generating station began in early 2008. A
preliminary feasibility assessment has been completed based on the
anticipated Darlington station refurbishment project scope and
expected post-refurbishment operating life. OPG is continuing with
technical, regulatory and preparatory work, and other analysis
related to refurbishing the Darlington nuclear generating station.
- In September 2009, OPG submitted its final Integrated Safety Review
report for the Pickering B nuclear generating station to the CNSC.
The report concludes that the Pickering B generating station
demonstrates a high level of compliance with modern codes and
standards. OPG anticipates approval of this report by the CNSC in
mid-2010. OPG is assessing a variety of options with respect to
future operations at the Pickering nuclear generating stations to
determine the preferred strategy for maximizing asset value,
including continued operations of the Pickering B nuclear generating
station units beyond the current nominal operating lives of 2014 to
2016.
Hydroelectric
- The Niagara tunnel boring machine ("TBM") had advanced 5,418 metres
as of September 30, 2009. The TBM reached the milestone of completing
50 percent of the tunnel excavation on August 4, 2009. The
advancement of the TBM has been temporarily interrupted since
September 11, 2009 to reinforce a short section of the temporary
tunnel liner that failed about 1,800 metres behind the current
location of the TBM. Installation of the permanent tunnel concrete
lining is progressing well and is ahead of the revised schedule.
Restoration of the circular cross-section of the tunnel before
installation of the upper two-thirds of the concrete lining began, as
planned, in September 2009.
- Construction of the Upper Mattagami and Hound Chute development
projects continued during the third quarter with fabrication of
supplied parts and systems, and delivery of certain major
Water-to-Wire equipment. The capacity of the four stations that are
being replaced will increase from 23 MW to 44 MW. The stations are
expected to be in service by April 2011. Total project costs are
expected to be $300 million.
- Definition phase activities for the planned Lower Mattagami
development to increase the capacity of four stations from 483 MW to
933 MW continued in the third quarter of 2009. Definition phase
activities include finalizing cost estimates, negotiating a
design-build contract, obtaining regulatory approvals, and
negotiating a Hydroelectric Energy Supply agreement with the Ontario
Power Authority.
Fossil
- In September 2009, together with the Ministry of Energy and
Infrastructure, OPG announced its decision to close four coal-fired
units - two units at the Lambton generating station and two units at
the Nanticoke generating station. The decision was based on the
impact of declining Ontario primary demand, forecast surplus capacity
and demand profiles, and reductions in operations, maintenance and
administration expense. The closures are expected to occur in
October 2010.
- The Lennox generating station operated under a reliability must run
contract with the Independent Electricity System Operator as approved
by the OEB for the period beginning on October 1, 2008 to
September 30, 2009. OPG continues to operate the facility and is in
discussions with the Government of Ontario regarding the issuance of
a Directive to the OPA to contract with OPG for the capacity of the
station for the period commencing October 1, 2009.
- The strategy to convert coal-fired units to alternate fuels continues
to advance. Detailed design engineering work on the conversion of the
Atikokan generating station to biomass is progressing. OPG is in
discussion with the Ministry of Energy and Infrastructure to
determine the appropriate mechanism for cost recovery associated with
electricity generation using biomass. A cost recovery mechanism is
needed prior to OPG issuing a request for proposal for fuel
procurement and seeking Board approval to proceed with plant
conversions. These two activities are contingent upon discussions
with the Ministry. OPG is conducting concept phase engineering for
the potential conversion of other coal-fired units.
FINANCIAL AND OPERATIONAL HIGHLIGHTS
-------------------------------------------------------------------------
Three Months Ended Nine Months Ended
(millions of dollars - September 30 September 30
except where noted) 2009 2008 2009 2008
-------------------------------------------------------------------------
Earnings
Revenue after revenue limit rebate 1,345 1,513 4,223 4,461
Fuel expense 249 334 730 915
-------------------------------------------------------------------------
Gross margin 1,096 1,179 3,493 3,546
-------------------------------------------------------------------------
Operations, maintenance and
administration expense 653 689 2,157 2,130
Depreciation and amortization 187 162 550 497
Accretion on fixed asset removal and
nuclear waste management liabilities 158 151 476 438
(Earnings) losses on nuclear fixed
asset removal and nuclear waste
management funds (254) 190 (549) 133
Other net expenses 28 24 72 61
-------------------------------------------------------------------------
Income before interest and income
taxes 324 (37) 787 287
Net interest expense 48 41 130 120
Income tax expenses (recoveries) 17 64 101 48
-------------------------------------------------------------------------
Net income 259 (142) 556 119
-------------------------------------------------------------------------
Cash flow
Cash flow (used in) provided by
operating activities 203 434 61 830
-------------------------------------------------------------------------
Income (loss) before interest and
income taxes
Generating segments 219 262 653 815
Nuclear Waste Management segment 96 (340) 75 (568)
Other segment 9 41 59 40
-------------------------------------------------------------------------
Total income before interest and
income taxes 324 (37) 787 287
-------------------------------------------------------------------------
Electricity Generation (TWh)
Regulated - Nuclear 12.9 12.2 34.4 35.6
Regulated - Hydroelectric 5.0 4.7 14.6 14.2
Unregulated - Hydroelectric 3.5 4.2 12.8 14.1
Unregulated - Fossil-Fuelled 1.2 6.2 7.3 18.7
Total electricity generation 22.6 27.3 69.1 82.6
Average electricity sales price
(cents/kWh)
Regulated - Nuclear 5.5 4.9 5.5 4.9
Regulated - Hydroelectric 3.7 3.8 3.7 3.6
Unregulated - Hydroelectric 2.4 4.8 3.2 4.7
Unregulated - Fossil-Fuelled 3.1 5.1 4.1 5.0
OPG average sales price 4.5 4.8 4.5 4.7
Nuclear unit capability factor
(percent)
Darlington 91.8 99.1 81.4 92.9
Pickering A 85.1 84.3 66.7 75.1
Pickering B 94.2 64.2 86.9 69.3
Equivalent forced outage rate
(percent)
Unregulated - Fossil-Fuelled 5.4 7.4 8.6 11.1
Availability (percent)
Regulated - Hydroelectric 93.2 93.9 93.7 93.4
Unregulated- Hydroelectric 87.2 93.5 93.3 95.6
-------------------------------------------------------------------------
-------------------------------------------------------------------------
Ontario Power Generation Inc. is an Ontario-based electricity generation company whose principal business is the generation and sale of electricity in Ontario. Our focus is on the efficient production and sale of electricity from our generation assets, while operating in a safe, open and environmentally responsible manner.
Ontario Power Generation Inc.'s unaudited consolidated financial statements and Management's Discussion and Analysis as at and for the three and nine months ended
For further information: Investor Relations, (416) 592-6700, 1-866-592-6700, [email protected]; Media Relations, (416) 592-4008, 1-877-592-4008
Share this article