/R E P E A T -- Champlain Bridge Corridor: Demolition of the north section of the Main Viaduct, complete closure of access ramps of the A-15 South and the A-15 North/ Français
LONGUEUIL, QC, April 8, 2015 /CNW Telbec/ - The Jacques Cartier and Champlain Bridges Incorporated (JCCBI) wishes to inform road users that phase 2 of work on the Main Viaduct will go on with the demolition of the north section during the period from Friday, April 10, 8 p.m. to Saturday, April 11, 8 p.m. These closures will be put in place:
Friday, April 10, 8 p.m. to Saturday, April 11, 11 a.m.
- Complete closure of the exit 60 ramp of A-15 South towards A-Bonaventure.
Friday, April 10, 8 p.m. to Saturday, April 11, 8 p.m.
- Complete closure of the exit 60 ramp of A-15 North.
- Complete closure of the exit 4 ramp of A-Bonaventure towards the A-15 North.
The Main Viaduct is located on the A-15 at the exit of the Île des Soeurs Bypass Bridge in Montreal. During phase 2 of the construction work, the north section of the viaduct will be demolished and rebuilt. This large-scale worksite will last until November and occasional closures may occur until then.
Please note that these closures could be postponed depending on expected weather conditions for the aforementioned dates. Visit our blog as of 3:30 p.m. on Friday, April 10, for more information regarding the planned work or any postponements: pontchamplainbridge.ca.
The Main Viaduct reconstruction worksite
In 2014, JCCBI carried out in phase 1 the demolition and reconstruction of the south section of the Main Viaduct. Phase 2 will take place this year on the north section.
Phase 2 will require occasional night closures, but no long-term closure will affect the A-15. Numerous efforts were made during the planning phase in order to maintain the number of lanes currently open on the A-15, namely two lanes in each direction throughout the work.
The size of the worksite will however require that the lanes be deviated and narrowed near the worksite located on the A-15.
To better understand the different phases of the worksite, please watch this video, which also explains the reconstruction of Viaducts N and V.
SOURCE The Jacques Cartier and Champlain Bridges Incorporated
Anne-Marie Braconnier, Acting Director of Communications, The Jacques Cartier and Champlain Bridges Incorporated (JCCBI), Mobile: 514 292-4493, [email protected]