/R E P E A T -- Île des Sœurs Bridge: concrete slab repair work planned over this weekend (November 16 & 17)/ Français
LONGUEUIL, QC, Nov. 12, 2013 /CNW Telbec/ - The Jacques Cartier and Champlain Bridges Incorporated (JCCBI) would like to advise road users that concrete slab repair work will continue on the Île des Sœurs Bridge in anticipation of the coming winter season during two to three weekends.
The work will take place from Friday, 11 p.m. at night to Monday, 5 a.m. in the morning on the weekend of November 16 & 17 (see the detailed configuration below), as well as on one or two other weekends (date to be confirmed).
Two lanes will be kept open to traffic in each direction during the day, but only one lane, reduced to three metres, will be open at night towards the South Shore.
Traffic may be heavier to access the Champlain Bridge from the Turcot Interchange during this period, as well as to access Montreal by the A-15 from the Champlain Bridge.
Road users are encouraged to favour the Bonaventure Expressway to access the Champlain Bridge or island of Montreal for the entire weekend.
Access and exit ramp closures
Access and exit ramps will also be closed on the network near the Île des Sœurs Bridge on Friday night, namely the access ramp from the Bonaventure Expressway to the A-15 South and North (Exit 4 of Bonaventure Expressway) at 9 p.m. and Exit 57-S of the A-15 South for access to Île des Sœurs at 11 p.m., these closures will occur for the entire weekend until Monday at 5 a.m.
The access ramp from Gaétan-Laberge Boulevard to the A-15 South (towards the Champlain Bridge) will be closed at night during the periods identified below.
Île des Sœurs Bridge lane configuration:
Second targeted weekend - November 16 & 17
At night: Friday, 11:00 p.m., to Saturday, 9:00 a.m.:
- One lane open towards the South Shore and two lanes open towards Montreal on the Île des Sœurs Bridge.
During the day: Saturday, 9:00 a.m. to 10:00 p.m.:
- Two lanes open per direction (South Shore and Montreal).
At night: Saturday, 10:00 p.m., to Sunday, 10:00 a.m.:
- One lane open towards the South Shore and two lanes open towards Montreal on the Île des Sœurs Bridge.
During the day: Sunday, 10:00 a.m. to 10:00 p.m.:
- Two lanes open per direction (South Shore and Montreal).
At night: Sunday, 10:00 p.m., to Monday, 5:00 a.m.:
- One lane open towards the South Shore and two lanes open towards Montreal on the Île des Sœurs Bridge.
To follow our work, we invite you to visit www.champlainbridge.ca.
SOURCE: The Jacques Cartier and Champlain Bridges Incorporated
Jean-Vincent Lacroix
Director, Communications
The Jacques Cartier and Champlain Bridges Incorporated (JCCBI)
Office: 450 651-8771, ext. 232
Cell: 514 249-1940
[email protected]
Share this article