Highlights - Appointment of leading engineering group to design, construct and commission the Kipoi Stage 1 treatment facilities. - Appointment of experienced consulting group to manage mining contractor tender process. - Appointment of qualified Mining Engineer as Project Manager. - Revised pit design work indicates potential to reduce pre-production mining period to 4 months and therefore reduce pre-production capital expenditure.
Design, construction and commissioning of treatment facilities
DRA Mineral Projects (Pty) Ltd of
DRA has designed and constructed Heavy Media Separation (HMS) plants for nickel mines in
Tiger has also appointed a qualified Mining Engineer to be the Project Manager and Tiger's representative to oversee the engineering work being conducted by DRA. He will be based in
Mining tender
Coffey Mining from Western
Revised pit design
In conjunction with experienced consultants the Company has recently completed a revised pit design for the Stage 1 development. The revised pit design work incorporates various improvements to increase the efficiency of mining operations, and also includes an alternative mine plan. The reworked mine plan has the potential to deliver a reduction in pre-production mining from six months to four months, thereby further reducing the pre-production capital expenditure and allowing the Stage 1 development to be brought into production earlier.
Development Timing
The Company continues to target commencement of production for mid 2010.
Additional Notes:
Caution Regarding Forward Looking Statements and Forward Looking Information: This release contains forward-looking statements and forward looking information, which are based on assumptions and judgments of management regarding future events and results. Such forward-looking statements and forward looking information, including but not limited to those with respect to the development of the Kipoi Project, involve known and unknown risks, uncertainties, and other factors which may cause the actual results, performance or achievements of the Company to be materially different from any anticipated future results, performance or achievements expressed or implied by such forward-looking statements. Such factors include, among others, the actual market prices of copper, cobalt and silver, the actual results of current exploration, the availability of debt financing for a company that does not have any producing properties, the volatility currently being experienced in global financial markets, the actual results of future mining, processing and development activities, changes in project parameters as plans continue to be evaluated, as well as those factors disclosed in the Company's Annual Information Form, under the heading "Risk Factors". The Company's Annual Information Form is available under the Company's profile on SEDAR at www.sedar.com.
For further information: in respect of the Company's activities, please contact: David Young, Managing Director, Tel: (+61 8) 9240 1933, Email: [email protected]; Reg Gillard, Chairman, Tel: (+61 8) 9240 1933, Email: [email protected]; Patrick Flint, Director, Tel: (+61 2) 9212 7999, Email: [email protected]; Company website: www.tigerresources.com.au
Share this article